| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 30 Aug 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 29 Aug 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 27 Aug 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 26 Aug 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. Interconnection work - 2 No.s. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 25 Aug 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 23 Aug 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 22 Aug 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 21 Aug 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 20 Aug 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 19 Aug 2025 | 90mm PVC pipe laying work in progress -1687m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -65 No.s. Interconnection 21 completed. 75mm PVC pipeline work ongoing. Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE |