Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Nov 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -182 No.s. Interconnection 21 completed.Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
24 Nov 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -180 No.s. Interconnection 21 completed.Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
21 Nov 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -172 No.s. Interconnection 21 completed.Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
20 Nov 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -170 No.s. Interconnection 21 completed.Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
19 Nov 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -170 No.s. Interconnection 21 completed.Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
18 Nov 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -165 No.s. Interconnection 21 completed.Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
17 Nov 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -150 No.s. Interconnection 21 completed.Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
14 Nov 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -150 No.s. Interconnection 21 completed.Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
13 Nov 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -150 No.s. Interconnection 21 completed.Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE
11 Nov 2025 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -150 No.s. Interconnection 21 completed.Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. Chathannur PH Sn AE