| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 25 Nov 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -182 No.s. Interconnection 21 completed.Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 24 Nov 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -180 No.s. Interconnection 21 completed.Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 21 Nov 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -172 No.s. Interconnection 21 completed.Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 20 Nov 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -170 No.s. Interconnection 21 completed.Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 19 Nov 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -170 No.s. Interconnection 21 completed.Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 18 Nov 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -165 No.s. Interconnection 21 completed.Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 17 Nov 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -150 No.s. Interconnection 21 completed.Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 14 Nov 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -150 No.s. Interconnection 21 completed.Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 13 Nov 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -150 No.s. Interconnection 21 completed.Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE | |
| 11 Nov 2025 | 90mm PVC pipe laying work in progress -1887m completed. 75mm PVC pipe laying work in progress -1500m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Geotagging of water connections -150 No.s. Interconnection 21 completed.Restoration works ongoing. Providing FHTCs from the existing water supply scheme work ongoing. | Chathannur PH Sn AE |