Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 May 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 50 No.s. Geotagging of water connections -47No.s. Interconnection 21 completed and remaining work ongoing. Chathannur PH Sn AE
28 May 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 50 No.s. Geotagging of water connections -47No.s. Interconnection 21 completed and remaining work ongoing. Chathannur PH Sn AE
27 May 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 50 No.s. Geotagging of water connections -47No.s. Interconnection 21 completed and remaining work ongoing. Chathannur PH Sn AE
26 May 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 50 No.s. Geotagging of water connections -47No.s. Interconnection 21 completed and remaining work ongoing. Chathannur PH Sn AE
26 May 2025 90mm PVC pipe laying work in progress -1487m completed. 75mm PVC pipe laying work in progress -1323m completed. Providing and fixing 65mm G.I pipe - 498m completed. Supply of 80mm G.I pipe- 498m completed. Fixing 80mm G.I pipe - 429m completed. Replacement of damaged connections- 116no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 50 No.s. Geotagging of water connections -47No.s. Interconnection 21 completed and remaining work ongoing. Chathannur PH Sn AE
26 May 2025 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 47 No.s. Geotagging of water connections -47No.s. Interconnection work ongoing. Chathannur PH Sn AE
24 May 2025 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 47 No.s. Geotagging of water connections -47No.s. Interconnection work ongoing. Chathannur PH Sn AE
23 May 2025 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 47 No.s. Geotagging of water connections -47No.s. Interconnection work ongoing Chathannur PH Sn AE
22 May 2025 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 47 No.s. Geotagging of water connections -47No.s. Interconnection work ongoing Chathannur PH Sn AE
21 May 2025 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 47 No.s. Geotagging of water connections -47No.s. Interconnection work ongoing Chathannur PH Sn AE