Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 Feb 2021 For Package I,proposal for demolition of 5.5 MLD and 1.5 MLD existing WTP is submitted to SE,PHCK for approval.Contractor has also being informed about this.Demolition of existing WTPS will accelerate the process of construction of Clariflocculator No1. For Package II,160 mm PVC pipes have arrived at site.Works for Mosco-Incherikunnu laying will begin in a while Kottayam Proj Dn AE4
05 Feb 2021 For Package II testing of HDPE pipes for next stretch is planned coming week starting 08.02.21 For Package II,Electrical approval for scheme has been obtained and works for subtation is about to begin Kottayam Proj Dn AE4
02 Feb 2021 76% for Package I & 8% for package II.For Packge II,HDPE pipe testing and jointing is in progress whereas for pakage I,Chemical store nd chlorine room foundation works along with aretaor RCC works for superstructure i in progress. Kottayam Proj Dn AE4
27 Jan 2021 76% of works completed for Package I 8% of works completed for Package II Kottayam Proj Dn AE4
12 Sep 2020 58% of works completed for package I Kottayam Proj Dn AE4
23 Jul 2020 49% of work completed for pkg-I Kottayam Proj Dn AE4
23 Jun 2020 45% of work for package I completed Kottayam Proj Dn AE4
22 Jun 2020 45% of work completed Kottayam Proj Dn AE4