Project | KIIFB-2016-17- WRD-002-09 Augmentation of UWSS to Kottayam Municipality |
---|---|
Project Code | KTMKIIFB0117545 |
Type | Main project |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Augmentation of UWSS to Kottayam Municipality which includes design,construction,commissioning of 50 MLD output capacity conventional type WTP and allied works at Peroor as package I & Supplying,laying,jointing,testing,commissioning of various sizes(600 to 150 mm) DI K9 pipes,710 mm HDPE pipes and distribution system at various places,supply and erection of clear water pump sets at KWA campus as Package II.Other 3 packages involve road restoration works along NH & PWD roads |
Status | On-going |
District | Kottayam |
Executing Office | Kottayam Project Dn |
AS Amount (Rs) | 500000000 |
AS Number | G.O(Rt) No14/2017/WRD/002-05 dated 11/01/2017 |
TS Amount (Rs) | 500000000 |
TS Number | KWA/P1/1035/2016-17/Part 9 |
Total Bill Submitted (Rs) | 258190068 |
Total Bill Paid (Rs) | 258190068 |
Population Benefitted | 208000 |
Capacity in MLD | 50.00 |
Actual Project Completion Date | 31 Dec 2023 |
Coverage | Kottayam municipality. Vijayapuram,Puthupally,Meenadom,Vakathanam |
Implementation Schedule | Download |
Work Plan | Download |
No. | Project Name | Location | View |
---|---|---|---|
1 | KIIFB-2016-17-WRD002-09- Augmentation of WSS to Kottayam Municipality, Package I-Design, Construction, testing and commissioning of 50 MLD output capacity water treatment plant and allied works at Peroor | Kottayam Project Dn | |
2 | KIIFB-2016-17-WRD 002-09- Augmentation of WSS to Kottayam Municipality, Package III- Restoration of road damaged by laying pipelines along NH 183 (MC Road) on both sides in Kottayam Municipal area under NH Roads Division, Kollam | Kottayam Project Dn | |
3 | KIIFB-2016-17-WRD002-09- Augmentation of WSS to Kottayam Municipality, Package II-Supplying,laying,testing and commissioning of various sizes of (600 mm to 150 mm) DI K9 pipes,710 mm HDPE pipes and distribution system at various places and supply and erection of clear water pumpsets at KWA campus pump house | Kottayam Project Dn | |
4 | KIIFB-2016-17-WRD 002-09- Augmentation of WSS to Kottayam Municipality, Package IV- Restoration of road damaged by laying pipelines along NH 183 (KK Road) on both sides in Kottayam Municipal area under NH Roads Division, Muvattupuzha | Kottayam Project Dn | |
5 | KIIFB-2016-17-WRD 002-09- Augmentation of WSS to Kottayam Municipality, Package V- Restoration of road damaged by laying pipelines along PWD Roads in Kottayam Municipal areas under PWD Roads Division, Kottayam | Kottayam Project Dn |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
08 Nov 2023 | **PACKAGE I** 95% of works completed. WTP is partially commissioned and water supply is made to Kottayam Municipality & adjoining Panchayaths. Energization works is in progress. Additional caution deposit of Rs 20.34 lacs is requested by KSEB for power enhancement for which fund request is made to KSEB.vOn reciept only 50 MLD can be commissioned. **PACKAGE 2** 65% work completed. Work is foreclosed on 16.12.2022 due to the non-availability of road cutting sanction from MoRTH on NH 183 on K.K road & M.C road.Bill is processed and uploaded to KIIFB**PACKAGE 3&4**This work involves road restoration on NH 183.Due to the non-availability of permission for laying pipes, restoration cannot be started. . **PACKAGE 5**This work involves road restoration on PWD roads. Out of restoration on 4 roads, all roads are completed and road is handed over to PWD for further works. | Kottayam Proj Dn AE4 | |
23 Jan 2023 | **PACKAGE I** 95% of works completed.WTP is partially commissioned and water supply is made to Kottayam Municipality & adjoining Panchayaths. Energization works is in progress.**PACKAGE 2** 65% work completed.Work is foreclosed on 16.12.2022 due to the non-availability of road cutting sanction from MoRTH on NH 183 on K.K road & M.C road.**PACKAGE 3&4**This work involves road restoration on NH 183.Due to the non-availability of permission for laying pipes, restoration cannot be started. . **PACKAGE 5**This work involves road restoration on PWD roads.Out of restoration on 4 roads,1 road is 100% completed,2 roads 95% completed & remaining 1 is 60% completed. | Kottayam Proj Dn AE4 | |
01 Aug 2022 | **PACKAGE I** 95% of works completed.All civil works is completed.Road tarring works is pending due to rainy season**PACKAGE 2** 63% work completed.95% of pipe laying works on sanction recieved PWD roads is completed now.Approx 12 km pipe laying is kept on hold due to non reciept of road cutting permission from MoRTH on NH 183. Appeal given to Chairman NHAI for permissions.Meeting with MoRTH officials is proposed on 01.08.2022 at the chamber of District Collector to discuss the way forward**PACKAGE 3&4** Road restoration works not started since pipe laying and road cutting has not begun on NH 183. **PACKAGE 5** PWD roa restoration works in progress.BM works completed over Kanjikuzhi-Muttambalam stretch whereas GSB filling completed on Erayil road stretch and on Mosco-Incherikunnu road stretch.Restoration works will be resumed after rain | Kottayam Proj Dn AE4 | |
10 Jul 2022 | **PACKAGE I** 95% of works completed.All civil works is completed.Electromechanical flowmeter erection works is completed. **PACKAGE 2** 62% work completed.95% of pipe laying works on sanction recieved PWD roads is completed now.Only interconnection works are pending.Approx 12 km pipe laying is kept on hold due to non reciept of road cutting permission from MoRTH on NH 183. Appeal given to Chairman NHAI for permissions**PACKAGE 3&4** Road restoration works not started since pipe laying and road cutting has not begun on NH 183. **PACKAGE 5** PWD roa restoration works in progress.BM works completed over Kanjikuzhi-Muttambalam stretch whereas GSB filling completed on Erayil road stretch and on Mosco-Incherikunnu road stretch | Kottayam Proj Dn AE4 | |
30 Jun 2022 | **PACKAGE I** 95% of works completed.All civil works is completed.Electromechanical flowmeter erection works in progress after that road tarring will be completed. **PACKAGE 2** 62% work completed.95% of pipe laying works on sanction recieved PWD roads is completed now.Only interconnection works are pending.Approx 12 km pipe laying is kept on hold due to non reciept of road cutting permission from MoRTH on NH 183. **PACKAGE 3&4** Road restoration works not started since pipe laying and road cutting has not begun on NH 183. **PACKAGE 5** PWD roa restoration works in progress.BM works completed over Kanjikuzhi-Muttambalam stretch whereas GSB filling completed on Erayil road stretch and on Mosco-Incherikunnu road stretch | Kottayam Proj Dn AE4 |
Review Date | Review Message | Review Attended By |
---|---|---|
04 Feb 2021 | Add sub project appproval as an issue for commissioning of the scheme | EE |
27 Jan 2021 | Sub Project approval for package 3 is to be obtained from KIIFB. EE Attach the letter submitted from HO to KIIFB for reference | EE |
Date of start of Project | 21/03/2018 |
---|---|
Scheduled date of Completion of the Project | 19 Sep 2019 |
Expected date of Completion | 16/12/2022 |
AS Date | 11 Jan 2017 |
---|---|
TS Date | 23 Jan 2017 |
Project Officers | View |
---|