KIIFB-2016-17- WRD-002-09 Augmentation of UWSS to Kottayam Municipality

Project KIIFB-2016-17- WRD-002-09 Augmentation of UWSS to Kottayam Municipality
Project Code KTMKIIFB0117545
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Augmentation of UWSS to Kottayam Municipality which includes design,construction,commissioning of 50 MLD output capacity conventional type WTP and allied works at Peroor as package I & Supplying,laying,jointing,testing,commissioning of various sizes(600 to 150 mm) DI K9 pipes,710 mm HDPE pipes and distribution system at various places,supply and erection of clear water pump sets at KWA campus as Package II.Other 3 packages involve road restoration works along NH & PWD roads
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
AS Amount (Rs) 500000000
AS Number G.O(Rt) No14/2017/WRD/002-05 dated 11/01/2017
TS Amount (Rs) 500000000
TS Number KWA/P1/1035/2016-17/Part 9
Total Bill Submitted (Rs) 258190068
Total Bill Paid (Rs) 258190068
Population Benefitted 208000
Capacity in MLD 50.00
Actual Project Completion Date 31 Dec 2023
Coverage Kottayam municipality. Vijayapuram,Puthupally,Meenadom,Vakathanam
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB-2016-17-WRD002-09- Augmentation of WSS to Kottayam Municipality, Package I-Design, Construction, testing and commissioning of 50 MLD output capacity water treatment plant and allied works at Peroor Kottayam Project Dn
2 KIIFB-2016-17-WRD 002-09- Augmentation of WSS to Kottayam Municipality, Package III- Restoration of road damaged by laying pipelines along NH 183 (MC Road) on both sides in Kottayam Municipal area under NH Roads Division, Kollam Kottayam Project Dn
3 KIIFB-2016-17-WRD002-09- Augmentation of WSS to Kottayam Municipality, Package II-Supplying,laying,testing and commissioning of various sizes of (600 mm to 150 mm) DI K9 pipes,710 mm HDPE pipes and distribution system at various places and supply and erection of clear water pumpsets at KWA campus pump house Kottayam Project Dn
4 KIIFB-2016-17-WRD 002-09- Augmentation of WSS to Kottayam Municipality, Package IV- Restoration of road damaged by laying pipelines along NH 183 (KK Road) on both sides in Kottayam Municipal area under NH Roads Division, Muvattupuzha Kottayam Project Dn
5 KIIFB-2016-17-WRD 002-09- Augmentation of WSS to Kottayam Municipality, Package V- Restoration of road damaged by laying pipelines along PWD Roads in Kottayam Municipal areas under PWD Roads Division, Kottayam Kottayam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Nov 2023 **PACKAGE I** 95% of works completed. WTP is partially commissioned and water supply is made to Kottayam Municipality & adjoining Panchayaths. Energization works is in progress. Additional caution deposit of Rs 20.34 lacs is requested by KSEB for power enhancement for which fund request is made to KSEB.vOn reciept only 50 MLD can be commissioned. **PACKAGE 2** 65% work completed. Work is foreclosed on 16.12.2022 due to the non-availability of road cutting sanction from MoRTH on NH 183 on K.K road & M.C road.Bill is processed and uploaded to KIIFB**PACKAGE 3&4**This work involves road restoration on NH 183.Due to the non-availability of permission for laying pipes, restoration cannot be started. . **PACKAGE 5**This work involves road restoration on PWD roads. Out of restoration on 4 roads, all roads are completed and road is handed over to PWD for further works. Kottayam Proj Dn AE4
23 Jan 2023 **PACKAGE I** 95% of works completed.WTP is partially commissioned and water supply is made to Kottayam Municipality & adjoining Panchayaths. Energization works is in progress.**PACKAGE 2** 65% work completed.Work is foreclosed on 16.12.2022 due to the non-availability of road cutting sanction from MoRTH on NH 183 on K.K road & M.C road.**PACKAGE 3&4**This work involves road restoration on NH 183.Due to the non-availability of permission for laying pipes, restoration cannot be started. . **PACKAGE 5**This work involves road restoration on PWD roads.Out of restoration on 4 roads,1 road is 100% completed,2 roads 95% completed & remaining 1 is 60% completed. Kottayam Proj Dn AE4
01 Aug 2022 **PACKAGE I** 95% of works completed.All civil works is completed.Road tarring works is pending due to rainy season**PACKAGE 2** 63% work completed.95% of pipe laying works on sanction recieved PWD roads is completed now.Approx 12 km pipe laying is kept on hold due to non reciept of road cutting permission from MoRTH on NH 183. Appeal given to Chairman NHAI for permissions.Meeting with MoRTH officials is proposed on 01.08.2022 at the chamber of District Collector to discuss the way forward**PACKAGE 3&4** Road restoration works not started since pipe laying and road cutting has not begun on NH 183. **PACKAGE 5** PWD roa restoration works in progress.BM works completed over Kanjikuzhi-Muttambalam stretch whereas GSB filling completed on Erayil road stretch and on Mosco-Incherikunnu road stretch.Restoration works will be resumed after rain Kottayam Proj Dn AE4
10 Jul 2022 **PACKAGE I** 95% of works completed.All civil works is completed.Electromechanical flowmeter erection works is completed. **PACKAGE 2** 62% work completed.95% of pipe laying works on sanction recieved PWD roads is completed now.Only interconnection works are pending.Approx 12 km pipe laying is kept on hold due to non reciept of road cutting permission from MoRTH on NH 183. Appeal given to Chairman NHAI for permissions**PACKAGE 3&4** Road restoration works not started since pipe laying and road cutting has not begun on NH 183. **PACKAGE 5** PWD roa restoration works in progress.BM works completed over Kanjikuzhi-Muttambalam stretch whereas GSB filling completed on Erayil road stretch and on Mosco-Incherikunnu road stretch Kottayam Proj Dn AE4
30 Jun 2022 **PACKAGE I** 95% of works completed.All civil works is completed.Electromechanical flowmeter erection works in progress after that road tarring will be completed. **PACKAGE 2** 62% work completed.95% of pipe laying works on sanction recieved PWD roads is completed now.Only interconnection works are pending.Approx 12 km pipe laying is kept on hold due to non reciept of road cutting permission from MoRTH on NH 183. **PACKAGE 3&4** Road restoration works not started since pipe laying and road cutting has not begun on NH 183. **PACKAGE 5** PWD roa restoration works in progress.BM works completed over Kanjikuzhi-Muttambalam stretch whereas GSB filling completed on Erayil road stretch and on Mosco-Incherikunnu road stretch Kottayam Proj Dn AE4

Project Review

See All Review messages
Review Date Review Message Review Attended By
04 Feb 2021 Add sub project appproval as an issue for commissioning of the scheme EE
27 Jan 2021 Sub Project approval for package 3 is to be obtained from KIIFB. EE Attach the letter submitted from HO to KIIFB for reference EE

Duration & Sanction dates

Date of start of Project 21/03/2018
Scheduled date of Completion of the Project 19 Sep 2019
Expected date of Completion 16/12/2022

Processing Dates

AS Date 11 Jan 2017
TS Date 23 Jan 2017