Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Apr 2021 ************************************* Package I:- 1. 80% is the progress of project. 2.Extension of Time of completion for Package I was granted till 31.03.2021 vide proceedings of SE,PHCK/A3/11/2015-Vol III by imposing a fine of Rs 50,000. 3.Physical progress of the components are as follows: (a)Aerator:-Finishing works in progress (b) Raw water channel:-Civil works in progress.Bypss channel supporting column erection works in progress. (c)Chemical store:Civil work till foundation beams completed and work is paused to divert more importance to other structural components. (d) Chlorine room:-Civil works completed.De shuttering has not commenced yet to facilitate brick works and jali works (e) Filter house:-Concreting of control chambers inside pipe gallery in progress.Other finishing works in progress. (f) Clariflocculator no:2-Civil works completed. Electro mechanical erection works not completed. (g) Substation yard works in progress. ************************************* Package II:- Progress of works is 14%. HDPE laying works in its final stretches. 160 mm PVC distribution laying and testing in progress Kottayam Proj Dn AE4
18 Mar 2021 Package II:- Progress of work is 14%. Kottayam Proj Dn AE4
18 Mar 2021 Package I:- 79% is the progress of project.The progress is shown as same for some time because of the following reasons: © AERATOR-Currently RCC works for super structure is in progress. On completion this shall for 0.62% of total work. (d) Raw water channel, flash mixer and bypass channel-Currently RCC works for super structure is in progress. On completion this shall for 0.55% of total work. (h) Filter House: Filter media supply accounts for 1.2% of work. Only gravel items for 1 nos filter bed is supplied (j) Chemical house: RCC works up to first floor accounts for 0.4% of total work (k)Chlorination units- RCC works up to first floor accounts for 0.5% of total work (l) Site protection works-Compound wall with barbed fencing accounts for 2% of total work.Only brick work is completed Though the % of completion of the above mentioned works are low,volume of works is more and time consuming. Kottayam Proj Dn AE4
17 Mar 2021 Progress of works for packages are as follows:- Package I:- 50 ML WTP at Peroor 1.Chlorine room roof slab shuttering works in progress. 2.Chemical house foundation plinth beam concreting in progress 3.Aerator steps reinforcement works nearing completion. 4.Bypass channel concrete works in progress 5.Compound wall construction nearing 400 m 6.General ground leveling works and filter house finishing works going on. Packge II:- Laying distribution system in Kottayam Municipality: 1.710 mm HDPE laying along Erayilkadavu bypass nearing completion 2.Distribution line 160 mm along with 710 mm HDPE laying in progress Kottayam Proj Dn AE4
15 Mar 2021 Package I:50 ML WTP at Peroor 1.Chlorine room roof slab shuttering works in progress. 2.Chemical house foundtion plinthbeam concreting in progress 3.Aerator steps reinforcement works nearing completion. 4.Bypass channel concrete works in progress 5.Compound wall construction nearing 400m 6.General ground levelling works and filter house finishing works going on Packge II:Laying distribution system in Kottayam Municipality: 1.710 mm HDPE laying nearing completion 2.Distribution line 160 mm along with 710 mm HDPE laying in progress Kottayam Proj Dn AE4
08 Mar 2021 Package I 1.Aerator collection tray works in progress 2.Chemical house and chlorine room-superstructure works in progress. 3.Raw water channel works in progress 4.Electrical wiring works for filter house in progress Package II 160 mm PVC laying along Erayil kadavu bypass roads started. Kottayam Proj Dn AE4
23 Feb 2021 Joint inspection by SE,PHCK,EE,PDK at site on 23.02.2021.Directed contractor to speed up the works for full commissioning by March 31 Kottayam Proj Dn AE4
23 Feb 2021 Package I As per the agreed terms of minutes of meeting on 10.02.2021,contractor was supposed to charge and commission 1 nos filter bed at new filter house..however the status of works as on today is as follows: 1.fikter media not supplied at site 2.backwash pumps etc not supplied at site 3.interconnection works for 1000 mm di k9 ravity main with existing sump is not started..specials were arranged from kwa side for urgency in work however the work has not progressed. The delay in works has been enquire with contractor,but response is not satisfactory. From kwa side,power enhancement estimate has been received and is send for fund request. Only thing pending from kwa side is handing over and permission to demolish 1.5 and 5.5 mld existing wtp at site.for this also partial commissioning of new 50 mld to be done by contractor. Package 2 Wotks in progress Kottayam Proj Dn AE4
16 Feb 2021 For Package I,As per agreed date of completion ,the works for charging filter bed is in progress.Interconnection works of Gravity Main is in progress.Anticipating to charge 1 nos filter bed by 20.02.2021 Kottayam Proj Dn AE4
12 Feb 2021 For Package I,Review of progress meeting of the project was held at the office of SE,PHCK. Contractor was also present.It was mutually agreed to charge and commission 1 nos of filter bed in the newly constructed filter house by 20.02.2021.All necessary arrangements for this including interconnection of existing gravity main 1000 mm DI K 9 with newly constructed sump ,interconnection of existing 600 mm DI K 9 pumping main with newly laid 1100 mm DI K 9 pumping main to pump water shall be completed by 20.02.2021. MoM is attached Kottayam Proj Dn AE4