Review Date | Review Message | Review Added By | Review Attended By |
---|---|---|---|
04 Feb 2021 | Add sub project appproval as an issue for commissioning of the scheme | Kottayam PH Circle SE | EE |
27 Jan 2021 | Sub Project approval for package 3 is to be obtained from KIIFB. EE Attach the letter submitted from HO to KIIFB for reference | Kottayam PH Circle SE | EE |
03 Feb 2021 | Add all the issues properly | Kottayam PH Circle SE | Exe.ENGINEER |