Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Nov 2023 **PACKAGE I** 95% of works completed. WTP is partially commissioned and water supply is made to Kottayam Municipality & adjoining Panchayaths. Energization works is in progress. Additional caution deposit of Rs 20.34 lacs is requested by KSEB for power enhancement for which fund request is made to KSEB.vOn reciept only 50 MLD can be commissioned. **PACKAGE 2** 65% work completed. Work is foreclosed on 16.12.2022 due to the non-availability of road cutting sanction from MoRTH on NH 183 on K.K road & M.C road.Bill is processed and uploaded to KIIFB**PACKAGE 3&4**This work involves road restoration on NH 183.Due to the non-availability of permission for laying pipes, restoration cannot be started. . **PACKAGE 5**This work involves road restoration on PWD roads. Out of restoration on 4 roads, all roads are completed and road is handed over to PWD for further works. Kottayam Proj Dn AE4
23 Jan 2023 **PACKAGE I** 95% of works completed.WTP is partially commissioned and water supply is made to Kottayam Municipality & adjoining Panchayaths. Energization works is in progress.**PACKAGE 2** 65% work completed.Work is foreclosed on 16.12.2022 due to the non-availability of road cutting sanction from MoRTH on NH 183 on K.K road & M.C road.**PACKAGE 3&4**This work involves road restoration on NH 183.Due to the non-availability of permission for laying pipes, restoration cannot be started. . **PACKAGE 5**This work involves road restoration on PWD roads.Out of restoration on 4 roads,1 road is 100% completed,2 roads 95% completed & remaining 1 is 60% completed. Kottayam Proj Dn AE4
01 Aug 2022 **PACKAGE I** 95% of works completed.All civil works is completed.Road tarring works is pending due to rainy season**PACKAGE 2** 63% work completed.95% of pipe laying works on sanction recieved PWD roads is completed now.Approx 12 km pipe laying is kept on hold due to non reciept of road cutting permission from MoRTH on NH 183. Appeal given to Chairman NHAI for permissions.Meeting with MoRTH officials is proposed on 01.08.2022 at the chamber of District Collector to discuss the way forward**PACKAGE 3&4** Road restoration works not started since pipe laying and road cutting has not begun on NH 183. **PACKAGE 5** PWD roa restoration works in progress.BM works completed over Kanjikuzhi-Muttambalam stretch whereas GSB filling completed on Erayil road stretch and on Mosco-Incherikunnu road stretch.Restoration works will be resumed after rain Kottayam Proj Dn AE4
10 Jul 2022 **PACKAGE I** 95% of works completed.All civil works is completed.Electromechanical flowmeter erection works is completed. **PACKAGE 2** 62% work completed.95% of pipe laying works on sanction recieved PWD roads is completed now.Only interconnection works are pending.Approx 12 km pipe laying is kept on hold due to non reciept of road cutting permission from MoRTH on NH 183. Appeal given to Chairman NHAI for permissions**PACKAGE 3&4** Road restoration works not started since pipe laying and road cutting has not begun on NH 183. **PACKAGE 5** PWD roa restoration works in progress.BM works completed over Kanjikuzhi-Muttambalam stretch whereas GSB filling completed on Erayil road stretch and on Mosco-Incherikunnu road stretch Kottayam Proj Dn AE4
30 Jun 2022 **PACKAGE I** 95% of works completed.All civil works is completed.Electromechanical flowmeter erection works in progress after that road tarring will be completed. **PACKAGE 2** 62% work completed.95% of pipe laying works on sanction recieved PWD roads is completed now.Only interconnection works are pending.Approx 12 km pipe laying is kept on hold due to non reciept of road cutting permission from MoRTH on NH 183. **PACKAGE 3&4** Road restoration works not started since pipe laying and road cutting has not begun on NH 183. **PACKAGE 5** PWD roa restoration works in progress.BM works completed over Kanjikuzhi-Muttambalam stretch whereas GSB filling completed on Erayil road stretch and on Mosco-Incherikunnu road stretch Kottayam Proj Dn AE4
02 Jun 2022 **PACKAGE I** 95% of works completed.All civil works is completed.Electromechanical flowmeter erection works in progress after that road tarring will be completed. **PACKAGE 2** 62% work completed.95% of pipe laying works on snaction recieved PWD roads is completed now.Only interconnection works are pending.Approx 12 km pipe laying is kept on hold due to non reciept of road cutting permission from MoRTH on NH 183. **PACKAGE 3&4** Road restoration works not started since pipe laying and road cutting has not begun on NH 183. **PACKAGE 5** PWD roa restoration works in progress.BM works completed over Kanjikuzhi-Muttambalam stretch whereas GSB filling completed on Erayil road stretch and is in progress on Mosco-Incherikunnu road stretch Kottayam Proj Dn AE4
19 Apr 2022 **Package I** 95% physical progress achieved.All majour civil construction works completed.Road tarring works is planned to be done after ongoing rain. **Package II** 60% physical progress for the work achieved.Gap work on 710 mm OD HDPE works completed.600 Di laying in progress along Balarama road.Inlet and outlet works for KWA campus OHSR,Mariyapally OHSR completed,95% works for inlet and outlet arrangement at Incherikunnu OHSR completed.Road cutting permission to lay pipes on MC road/KK Road is not yet obtained. **Package 3&4** Not started due to permission from MoRTH is pending **Package 5** 16% progress.Remaining tarring works on PWD roads will commence after rain Kottayam Proj Dn AE4
17 Mar 2022 **Package I** 93% physical progress achieved.All majour civil construction works completed.Plastering works for clariflocculator,valve chamber works,finishing works etc in progress. **Package II** 60% physical progress for the work achieved.Gap work on 710 mm OD HDPE works completed.600 Di laying in progress along Balarama road.Inlet and outlet works for KWA campus OHSR,Mariyapally OHSR completed,95% works for inlet and outlet arrangement at Incherikunnu OHSR completed.Gap closing works on Kanjirapally road is progressing.Road cutting permission to lay pipes on MC road/KK Road is not yet obtained. **Package 3&4** Not started due to permission from MoRTH is pending **Package 5** 16% progress.Remaining tarring works on PWD roads will commence once the gap pworks are completed. Kottayam Proj Dn AE4
02 Feb 2022 **PACKAGE 3&4** Not started since this work involves Road Restoration on NH 183 for which permission for laying pipes is denied by MoRTH. **PACKAGE 5** Road restoration on PWD roads.This work is progressing and 16% is completed Kottayam Proj Dn AE4
02 Feb 2022 **PACKAGE I** 91% physical progress. Clariflocculator side wall concreting in progress.Landscaping and interconnection works is nearing completion.No hindrance to work. **PACKAGE II** 57% physical progress.Pipe laying on all roads except on NH 183 is progressing at a faster rate. Kottayam Proj Dn AE4