Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
06 Jul 2023 | OUT OF 3188 FHTC, 2002 HTC COMPLETED, 50 mm PVC pipe -16623/21000m as laid. 10th and part bill submitted. | Mathilakam AE | |
03 Jul 2023 | OUT OF 3188 FHTC, 1999 HTC COMPLETED, 50 mm PVC pipe -16473/21000m as laid. 10th and part bill submitted. | Mathilakam AE | |
29 Jun 2023 | OUT OF 3188 FHTC, 1915 HTC COMPLETED, 50 mm PVC pipe -16473/21000m as laid. 10th and part bill submitted. | Mathilakam AE | |
26 Jun 2023 | OUT OF 3188 FHTC, 1852 HTC COMPLETED, 50 mm PVC pipe -16473/21000m as laid. 10th and part bill submitted. | Mathilakam AE | |
22 Jun 2023 | OUT OF 3188 FHTC, 1824 HTC COMPLETED, 50 mm PVC pipe -16473/21000m as laid. 10th and part bill submitted. | Mathilakam AE | |
19 Jun 2023 | OUT OF 3188 FHTC, 1796 HTC COMPLETED, 50 mm PVC pipe -16473/21000m as laid. 10th and part bill submitted. | Mathilakam AE | |
15 Jun 2023 | OUT OF 3188 FHTC, 1796 HTC COMPLETED, 50 mm PVC pipe -16473/21000m as laid. 10th and part bill submitted. | Mathilakam AE | |
13 Jun 2023 | OUT OF 3188 FHTC, 1779 HTC COMPLETED, 50 mm PVC pipe -16473/21000m as laid | Mathilakam AE | |
06 Jun 2023 | OUT OF 3188 FHTC, 1754 HTC COMPLETED, 50 mm PVC pipe -16428/21000m as laid | Mathilakam AE | |
01 Jun 2023 | OUT OF 3188 FHTC, 1732 HTC COMPLETED, 50 mm PVC pipe -15900/21000m as laid | Mathilakam AE |