Overall Project Status

Status Date Overall Project Status Project Officer Contact
06 Jul 2023 OUT OF 3188 FHTC, 2002 HTC COMPLETED, 50 mm PVC pipe -16623/21000m as laid. 10th and part bill submitted. Mathilakam AE
03 Jul 2023 OUT OF 3188 FHTC, 1999 HTC COMPLETED, 50 mm PVC pipe -16473/21000m as laid. 10th and part bill submitted. Mathilakam AE
29 Jun 2023 OUT OF 3188 FHTC, 1915 HTC COMPLETED, 50 mm PVC pipe -16473/21000m as laid. 10th and part bill submitted. Mathilakam AE
26 Jun 2023 OUT OF 3188 FHTC, 1852 HTC COMPLETED, 50 mm PVC pipe -16473/21000m as laid. 10th and part bill submitted. Mathilakam AE
22 Jun 2023 OUT OF 3188 FHTC, 1824 HTC COMPLETED, 50 mm PVC pipe -16473/21000m as laid. 10th and part bill submitted. Mathilakam AE
19 Jun 2023 OUT OF 3188 FHTC, 1796 HTC COMPLETED, 50 mm PVC pipe -16473/21000m as laid. 10th and part bill submitted. Mathilakam AE
15 Jun 2023 OUT OF 3188 FHTC, 1796 HTC COMPLETED, 50 mm PVC pipe -16473/21000m as laid. 10th and part bill submitted. Mathilakam AE
13 Jun 2023 OUT OF 3188 FHTC, 1779 HTC COMPLETED, 50 mm PVC pipe -16473/21000m as laid Mathilakam AE
06 Jun 2023 OUT OF 3188 FHTC, 1754 HTC COMPLETED, 50 mm PVC pipe -16428/21000m as laid Mathilakam AE
01 Jun 2023 OUT OF 3188 FHTC, 1732 HTC COMPLETED, 50 mm PVC pipe -15900/21000m as laid Mathilakam AE