Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Jun 2024 | OUT OF 3188 FHTC, 2906 HTC COMPLETED, 50 mm PVC pipe -20934.5/21000m as laid. 14th and part bill submitted.connection work and measurement ongoing. | Mathilakam AE | |
20 Jun 2024 | OUT OF 3188 FHTC, 2906 HTC COMPLETED, 50 mm PVC pipe -20934.5/21000m as laid. 14th and part bill submitted.connection work and measurement ongoing. | Mathilakam AE | |
11 Jun 2024 | OUT OF 3188 FHTC, 2906 HTC COMPLETED, 50 mm PVC pipe -20934.5/21000m as laid. 14th and part bill submitted.connection work and measurement ongoing. | Mathilakam AE | |
05 Jun 2024 | OUT OF 3188 FHTC, 2906 HTC COMPLETED, 50 mm PVC pipe -20934.5/21000m as laid. 14th and part bill submitted.connection work and measurement ongoing. | Mathilakam AE | |
21 May 2024 | OUT OF 3188 FHTC, 2906 HTC COMPLETED, 50 mm PVC pipe -20934.5/21000m as laid. 14th and part bill submitted.connection work and measurement ongoing. | Mathilakam AE | |
13 May 2024 | OUT OF 3188 FHTC, 2906 HTC COMPLETED, 50 mm PVC pipe -20934.5/21000m as laid. 14th and part bill submitted.connection work and measurement ongoing. | Mathilakam AE | |
06 May 2024 | OUT OF 3188 FHTC, 2906 HTC COMPLETED, 50 mm PVC pipe -20934.5/21000m as laid. 13th and part bill submitted.connection work and measurement ongoing. | Mathilakam AE | |
23 Apr 2024 | OUT OF 3188 FHTC, 2906 HTC COMPLETED, 50 mm PVC pipe -19500/21000m as laid. 13th and part bill submitted.connection work and measurement ongoing. | Mathilakam AE | |
17 Apr 2024 | OUT OF 3188 FHTC, 2906 HTC COMPLETED, 50 mm PVC pipe -19500/21000m as laid. 13th and part bill submitted.connection work and measurement ongoing. | Mathilakam AE | |
04 Apr 2024 | OUT OF 3188 FHTC, 2906 HTC COMPLETED, 50 mm PVC pipe -19500/21000m as laid. 13th and part bill submitted.connection work and measurement ongoing. | Mathilakam AE |