Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
31 Oct 2023 | OUT OF 3188 FHTC, 2547 HTC COMPLETED, 50 mm PVC pipe -18832.95/21000m as laid. 13th and part bill submitted | Mathilakam AE | |
28 Oct 2023 | OUT OF 3188 FHTC, 2547 HTC COMPLETED, 50 mm PVC pipe -18832.95/21000m as laid. 13th and part bill submitted | Mathilakam AE | |
21 Oct 2023 | OUT OF 3188 FHTC, 2531 HTC COMPLETED, 50 mm PVC pipe -18832.95/21000m as laid. 13th and part bill submitted | Mathilakam AE | |
18 Oct 2023 | OUT OF 3188 FHTC, 2511 HTC COMPLETED, 50 mm PVC pipe -18832.95/21000m as laid. 13th and part bill submitted | Mathilakam AE | |
10 Oct 2023 | OUT OF 3188 FHTC, 2511 HTC COMPLETED, 50 mm PVC pipe -18832.95/21000m as laid. 13th and part bill submitted | Mathilakam AE | |
05 Oct 2023 | OUT OF 3188 FHTC, 2511 HTC COMPLETED, 50 mm PVC pipe -18832.95/21000m as laid. 13th and part bill submitted | Mathilakam AE | |
02 Oct 2023 | OUT OF 3188 FHTC, 2511 HTC COMPLETED, 50 mm PVC pipe -18832.95/21000m as laid. 13th and part bill submitted | Mathilakam AE | |
29 Sep 2023 | OUT OF 3188 FHTC, 2503 HTC COMPLETED, 50 mm PVC pipe -18832.95/21000m as laid. 13th and part bill submitted | Mathilakam AE | |
25 Sep 2023 | OUT OF 3188 FHTC, 2503 HTC COMPLETED, 50 mm PVC pipe -18832.95/21000m as laid. 13th and part bill submitted | Mathilakam AE | |
19 Sep 2023 | OUT OF 3188 FHTC, 2482 HTC COMPLETED, 50 mm PVC pipe -16623/21000m as laid. 13th and part bill submitted | Mathilakam AE |