Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
23 Mar 2023 | OUT OF 3188 FHTC, 929 HTC COMPLETED, 50 mm PVC pipe -12630/13000m as laid | Mathilakam AE | |
21 Mar 2023 | OUT OF 3188 FHTC, 887 HTC COMPLETED, 50 mm PVC pipe -12500/13000m as laid | Mathilakam AE | |
16 Mar 2023 | OUT OF 3188 FHTC, 501 HTC COMPLETED, 50 mm PVC pipe -9788/13000m as laid | Mathilakam AE | |
14 Mar 2023 | OUT OF 3188 FHTC, 501 HTC COMPLETED, 50 mm PVC pipe -9600/13000m as laid | Mathilakam AE | |
13 Mar 2023 | OUT OF 3188 FHTC, 501 HTC COMPLETED, 50 mm PVC pipe -9141/13000m as laid | Mathilakam AE | |
09 Mar 2023 | OUT OF 3188 FHTC, 501 HTC COMPLETED, 50 mm PVC pipe -9141/13000m as laid | Mathilakam AE | |
07 Mar 2023 | OUT OF 3188 FHTC, 501 HTC COMPLETED, 50 mm PVC pipe -9141/13000m as laid | Mathilakam AE | |
02 Mar 2023 | OUT OF 3188 FHTC, 501 HTC COMPLETED, 50 mm PVC pipe -8457/13000m as laid | Mathilakam AE | |
24 Feb 2023 | OUT OF 3188 FHTC, 501 HTC COMPLETED, 50 mm PVC pipe -8321/13000m as laid | Mathilakam AE | |
14 Feb 2023 | OUT OF 3188 FHTC, 413 HTC COMPLETED, 50 mm PVC pipe -7781/13008m as laid | Mathilakam AE |