Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
16 Jan 2023 | First and part bill submitted | Mathilakam AE | |
13 Jan 2023 | 50 mm PVC pipe laid -4554m | Mathilakam AE | |
10 Jan 2023 | 50 mm PVC pipe laid -4514m | Mathilakam AE | |
07 Jan 2023 | 50 mm PVC pipe laid -3291m | Mathilakam AE | |
04 Jan 2023 | 50 mm PVC pipe laid -3291m | Mathilakam AE | |
30 Dec 2022 | 50 mm PVC pipe laid -2673m | Mathilakam AE | |
28 Dec 2022 | 50 mm PVC pipe laid -2371m | Mathilakam AE | |
26 Dec 2022 | 50 mm PVC pipe laid -1847m | Mathilakam AE | |
23 Dec 2022 | 50 mm PVC pipe supplied -13008m | Mathilakam AE | |
23 Dec 2022 | NHAI Joint inspection completed | Mathilakam AE |