Status Date Overall Project Status Project Officer Contact
09 Feb 2023 OUT OF 3188 FHTC, 362 HTC COMPLETED, 50 mm PVC pipe -7738m as laid Mathilakam AE
06 Feb 2023 OUT OF 3188 FHTC, 316 HTC COMPLETED, 50 mm PVC pipe -6897m as laid Mathilakam AE
02 Feb 2023 OUT OF 3188 FHTC, 228 HTC COMPLETED, 50 mm PVC pipe -6778m as laid. Mathilakam AE
02 Feb 2023 OUT OF 3188 FHTC, 197 HTC COMPLETED, 50 mm PVC pipe -6778m as laid. Mathilakam AE
30 Jan 2023 OUT OF 3188 FHTC, 197 HTC COMPLETED, 50 mm PVC pipe -6778m as laid. Mathilakam AE
24 Jan 2023 OUT OF 3188 FHTC, 56 HTC COMPLETED, 50 mm PVC pipe -6312m as laid. Mathilakam AE
20 Jan 2023 OUT OF 3188 FHTC, 26 HTC COMPLETED, 50 mm PVC pipe -5906.5m as laid. Mathilakam AE
20 Jan 2023 OUT OF 3188 FHTC, 26 HTC COMPLETED, 50 mm PVC pipe -3615.5 m as laid. Mathilakam AE
19 Jan 2023 OUT OF 3188 FHTC, 26 HTC COMPLETED, 50 mm PVC pipe -5595 m as laid. Mathilakam AE
17 Jan 2023 50 mm PVC pipe laid -5018 m Mathilakam AE