Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
09 Feb 2023 | OUT OF 3188 FHTC, 362 HTC COMPLETED, 50 mm PVC pipe -7738m as laid | Mathilakam AE | |
06 Feb 2023 | OUT OF 3188 FHTC, 316 HTC COMPLETED, 50 mm PVC pipe -6897m as laid | Mathilakam AE | |
02 Feb 2023 | OUT OF 3188 FHTC, 228 HTC COMPLETED, 50 mm PVC pipe -6778m as laid. | Mathilakam AE | |
02 Feb 2023 | OUT OF 3188 FHTC, 197 HTC COMPLETED, 50 mm PVC pipe -6778m as laid. | Mathilakam AE | |
30 Jan 2023 | OUT OF 3188 FHTC, 197 HTC COMPLETED, 50 mm PVC pipe -6778m as laid. | Mathilakam AE | |
24 Jan 2023 | OUT OF 3188 FHTC, 56 HTC COMPLETED, 50 mm PVC pipe -6312m as laid. | Mathilakam AE | |
20 Jan 2023 | OUT OF 3188 FHTC, 26 HTC COMPLETED, 50 mm PVC pipe -5906.5m as laid. | Mathilakam AE | |
20 Jan 2023 | OUT OF 3188 FHTC, 26 HTC COMPLETED, 50 mm PVC pipe -3615.5 m as laid. | Mathilakam AE | |
19 Jan 2023 | OUT OF 3188 FHTC, 26 HTC COMPLETED, 50 mm PVC pipe -5595 m as laid. | Mathilakam AE | |
17 Jan 2023 | 50 mm PVC pipe laid -5018 m | Mathilakam AE |