Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
16 Sep 2023 | OUT OF 3188 FHTC, 2482 HTC COMPLETED, 50 mm PVC pipe -16623/21000m as laid. 13th and part bill submitted | Mathilakam AE | |
14 Sep 2023 | OUT OF 3188 FHTC, 2482 HTC COMPLETED, 50 mm PVC pipe -16623/21000m as laid. 12th and part bill submitted | Mathilakam AE | |
11 Sep 2023 | OUT OF 3188 FHTC, 2457 HTC COMPLETED, 50 mm PVC pipe -16623/21000m as laid. 12th and part bill submitted | Mathilakam AE | |
07 Sep 2023 | OUT OF 3188 FHTC, 2418 HTC COMPLETED, 50 mm PVC pipe -16623/21000m as laid. 12th and part bill submitted | Mathilakam AE | |
04 Sep 2023 | OUT OF 3188 FHTC, 2418 HTC COMPLETED, 50 mm PVC pipe -16623/21000m as laid. 12th and part bill submitted | Mathilakam AE | |
01 Sep 2023 | OUT OF 3188 FHTC, 2418 HTC COMPLETED, 50 mm PVC pipe -16623/21000m as laid. 12th and part bill submitted | Mathilakam AE | |
24 Aug 2023 | OUT OF 3188 FHTC, 2418 HTC COMPLETED, 50 mm PVC pipe -16623/21000m as laid. 12th and part bill submitted | Mathilakam AE | |
21 Aug 2023 | OUT OF 3188 FHTC, 2418 HTC COMPLETED, 50 mm PVC pipe -16623/21000m as laid. 12th and part bill submitted. | Mathilakam AE | |
17 Aug 2023 | OUT OF 3188 FHTC, 2418 HTC COMPLETED, 50 mm PVC pipe -16623/21000m as laid. 12th and part bill submitted. | Mathilakam AE | |
14 Aug 2023 | OUT OF 3188 FHTC, 2285 HTC COMPLETED, 50 mm PVC pipe -16623/21000m as laid. 11th and part bill submitted. | Mathilakam AE |