Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Apr 2023 | OUT OF 3188 FHTC, 1300 HTC COMPLETED, 50 mm PVC pipe -12866/13000m as laid | Mathilakam AE | |
24 Apr 2023 | OUT OF 3188 FHTC, 1273 HTC COMPLETED, 50 mm PVC pipe -12866/13000m as laid | Mathilakam AE | |
20 Apr 2023 | OUT OF 3188 FHTC, 1273 HTC COMPLETED, 50 mm PVC pipe -12866/13000m as laid | Mathilakam AE | |
17 Apr 2023 | OUT OF 3188 FHTC, 1192 HTC COMPLETED, 50 mm PVC pipe -12866/13000m as laid | Mathilakam AE | |
13 Apr 2023 | OUT OF 3188 FHTC, 1141 HTC COMPLETED, 50 mm PVC pipe -12866/13000m as laid | Mathilakam AE | |
10 Apr 2023 | OUT OF 3188 FHTC, 1062 HTC COMPLETED, 50 mm PVC pipe -12866/13000m as laid | Mathilakam AE | |
06 Apr 2023 | OUT OF 3188 FHTC, 1062 HTC COMPLETED, 50 mm PVC pipe -12866/13000m as laid | Mathilakam AE | |
04 Apr 2023 | OUT OF 3188 FHTC, 1062 HTC COMPLETED, 50 mm PVC pipe -12866/13000m as laid | Mathilakam AE | |
30 Mar 2023 | OUT OF 3188 FHTC, 929 HTC COMPLETED, 50 mm PVC pipe -12866/13000m as laid | Mathilakam AE | |
27 Mar 2023 | OUT OF 3188 FHTC, 929 HTC COMPLETED, 50 mm PVC pipe -12680/13000m as laid | Mathilakam AE |