Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Feb 2021 KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attains a progress of 38.01%, Package 2 Pooyapally Village attains a progress of 92.86%, Package 3 Meenad Village attains a progress of 84.82% ,Package 4 Chirakkara Village attains a progress of 95.89% ,Package 5 Paravoor Part Village attains a progress of 100% ,Package 6 Poothakulam Village attains a progress of 27.1%, Package 7 Adichanaloor Village attains a progress of 9.62%. Kollam Project HD
30 Jan 2021 Works at POOTHAKULAM package 6 - 28 percent completed and work at paravur municipality 1 - 33 percent completed Kollam Project HD
10 Dec 2020 "All packages work in progress.PackageV-Completed,Package I- 26% completed, Package II-72% completed,Package III-31% completed,Package IV- 50% completed, Package VI-24% completed,Package VII- 7% completed. Kollam Project HD
15 Nov 2020 "work in progress.PackageII-40km laid out of 61.08 km,interconnection and testing in progress(66%)Package I-2000 m laid (11%)PackageIII-8.3km laid out of 26.9km(29%),Package4- 18.8 km laid , Hydro testing of pipe line in progress ,GI pipe line works in progress (50%)PackageV- Work completed(100%),PackageVI-Work in progress 3.2km completed.(12%)PackageVI-4.5 km laid out of 71 km ,pipe suppl in progress(7%)" Kollam Project HD
01 Jul 2020 . PIU 1 - AE 2