Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Oct 2021 Out of 7 packages 4 works completed...adichanaloor package ongoing and No work restarted and not supplied balance pipe and notice issued for termination and for arranging works risk and cost for POOTHAKULAM and for paravoor municipality.. requested time extension granted upto 31.12.2021 Kollam Project HD
16 Oct 2021 Out of 7 packages 4 works completed...adichanaloor package ongoing and No work restarted and not supplied balance pipe and notice issued for termination and for arranging works risk and cost for POOTHAKULAM and for paravoor municipality.. contractor requested time extension request Kollam Project HD
10 Oct 2021 No work restarted and not supplied balance pipe and notice issued for termination and for arranging works risk and cost for POOTHAKULAM and for paravoor municipality.. contractor requested time extension request Kollam Project HD
02 Oct 2021 No progress or work restarted POOTHAKULAM ( package vi and Paravoor Municipality ( package I).. For package one contractor has submitted schedule for work completion. Kollam Project HD
11 Sep 2021 No progress or work started at paravoor municipality and POOTHAKULAM Panchayat...notice issued several times to the concerned contractor..Now it is forced to terminate the work and may arrange at the risk and cost of the contractor Kollam Project HD
14 Aug 2021 Work not started and intimated the contractor for immediate commencement of work. The work may be arranged at his risk and cost for paravoor municipality and POOTHAKULAM Kollam Project HD
17 Jul 2021 Review meeting done on 16.07.2021..by Hon. chathenoor MLA... directed for speedy completion of work and for taking balance estimate for full coverage in all areas under chathenoor constituency...Work not started... contractors ( paravoor and POOTHAKULAM packaged)was called for a meeting on 22.06.2021 for speedy completion of work and directed to submit revised working schedule and supply balance pipe Kollam Project HD
12 Jul 2021 2021 Work stopped due to Lock down restrictions and some of the labours tested COVID 19- positive, KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46% - interconnection works in progress...Package 2 Pooyapally Village attained a laying progress of 100%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 48%, Package 7 Adichanaloor Village attained a laying progress of 12%, temporary stopped For POOTHAKULAM grama Panchayat - 14.7 km laid out of 32.56 km and for paravoor 7.4km laid out of 17.16 km - Directed to start the work, but no reponse from the contractor Kollam Project HD
07 Jul 2021 Work not started... contractors ( paravoor and POOTHAKULAM packaged)was called for a meeting on 22.06.2021 for speedy completion of work and directed to submit revised working schedule and supply balance pipe. But no positive reply from the concerned contractors... Adichanaloor Package works restarted. Kollam Project HD
03 Jul 2021 Work not started... contractors ( paravoor and POOTHAKULAM packaged)was called for a meeting on 22.06.2021 for speedy completion of work and directed to submit revised working schedule and supply balance pipe.Adichanaloor Package works restarted. Kollam Project HD