Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Mar 2021 Work for survey and boundary demarcation by revenue in progress Kollam Project HD
20 Mar 2021 KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46% - no work , Package 2 Pooyapally Village attained a laying progress of 96%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 46%, Package 7 Adichanaloor Village attained a laying progress of 11% Kollam Project HD
19 Mar 2021 KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46%, Package 2 Pooyapally Village attained a laying progress of 96%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 45%, Package 7 Adichanaloor Village attained a laying progress of 10% Kollam Project HD
17 Mar 2021 KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46%, Package 2 Pooyapally Village attained a laying progress of 96%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 45%, Package 7 Adichanaloor Village attained a laying progress of 10% Kollam Project HD
16 Mar 2021 KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46%, Package 2 Pooyapally Village attained a laying progress of 96%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 45%, Package 7 Adichanaloor Village attained a laying progress of 10% Kollam Project HD
08 Mar 2021 KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46%, Package 2 Pooyapally Village attained a laying progress of 96%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 45%, Package 7 Adichanaloor Village attained a laying progress of 10% Kollam Project HD
05 Mar 2021 KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 43%, Package 2 Pooyapally Village attained a laying progress of 95%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 41%, Package 7 Adichanaloor Village attained a laying progress of 9%. Kollam Project HD
27 Feb 2021 Package 1 ...43percentage completed and package 6.... 41 percentage completed Kollam Project HD
22 Feb 2021 KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 38.01%, Package 2 Pooyapally Village attained a laying progress of 92.86%, Package 3 Meenad Village attained a laying progress of 88.76% ,Package 4 Chirakkara Village attained a laying progress of 95.92% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 27.1%, Package 7 Adichanaloor Village attained a laying progress of 9.62%. Kollam Project HD
15 Feb 2021 KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attains a progress of 38.01%, Package 2 Pooyapally Village attains a progress of 92.86%, Package 3 Meenad Village attains a progress of 85% ,Package 4 Chirakkara Village attains a progress of 95% ,Package 5 Paravoor Part Village attains a progress of 100% ,Package 6 Poothakulam Village attains a progress of 35%, Package 7 Adichanaloor Village attains a progress of 9.62% Kollam Project HD