Status Date |
Overall Project Status |
Project Officer |
Contact |
21 Apr 2021 |
KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46% - interconnection works in progress...Package 2 Pooyapally Village attained a laying progress of 100%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 48%, Package 7 Adichanaloor Village attained a laying progress of 12%, temporary stopped For POOTHAKULAM grama Panchayat - 14.7 km laid out of 32.56 km and for paravoor 7.4km laid out of 17.16 km |
Kollam Project HD |
|
20 Apr 2021 |
KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46% - interconnection works in progress...Package 2 Pooyapally Village attained a laying progress of 100%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 48%, Package 7 Adichanaloor Village attained a laying progress of 12%, temporary stopped For POOTHAKULAM grama Panchayat - 14.7 km laid out of 32.56 km and for paravoor 7.4km laid out of 17.16 km |
Kollam Project HD |
|
17 Apr 2021 |
KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46% - temporary stopped, Package 2 Pooyapally Village attained a laying progress of 100%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 48%, Package 7 Adichanaloor Village attained a laying progress of 12%, temporary stopped For POOTHAKULAM grama Panchayat - 14.4 km laid out of 32.56 km and for paravoor 7.3 km laid out of 17.16 km |
Kollam Project HD |
|
15 Apr 2021 |
KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46% - temporary stopped, Package 2 Pooyapally Village attained a laying progress of 100%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 48%, Package 7 Adichanaloor Village attained a laying progress of 12%, temporary stopped
For POOTHAKULAM grama Panchayat - 14.3 km laid out of 32.56 km and for paravoor 7.3 km laid out of 17.16 km |
Kollam Project HD |
|
12 Apr 2021 |
KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46% - temporary stopped, Package 2 Pooyapally Village attained a laying progress of 100%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 48%, Package 7 Adichanaloor Village attained a laying progress of 12%, temporary stopped |
Kollam Project HD |
|
03 Apr 2021 |
KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46% - , Package 2 Pooyapally Village attained a laying progress of 100%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 47%, Package 7 Adichanaloor Village attained a laying progress of 12% |
Kollam Project HD |
|
01 Apr 2021 |
KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46% - , Package 2 Pooyapally Village attained a laying progress of 100%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 46%, Package 7 Adichanaloor Village attained a laying progress of 11% |
Kollam Project HD |
|
29 Mar 2021 |
KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46% - no work , Package 2 Pooyapally Village attained a laying progress of 96%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 46%, Package 7 Adichanaloor Village attained a laying progress of 11% |
Kollam Project HD |
|
24 Mar 2021 |
KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46% - no work , Package 2 Pooyapally Village attained a laying progress of 96%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 46%, Package 7 Adichanaloor Village attained a laying progress of 11% |
Kollam Project HD |
|
22 Mar 2021 |
KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46% - no work , Package 2 Pooyapally Village attained a laying progress of 96%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 46%, Package 7 Adichanaloor Village attained a laying progress of 11% |
Kollam Project HD |
|