Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Jun 2021 Work not started... contractors ( paravoor and POOTHAKULAM packaged)was called for a meeting on 22.06.2021 for speedy completion of work and directed to submit revised working schedule and supply balance pipe Kollam Project HD
19 Jun 2021 2021 Work stopped due to Lock down restrictions and some of the labours tested COVID 19- positive, KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46% - interconnection works in progress...Package 2 Pooyapally Village attained a laying progress of 100%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 48%, Package 7 Adichanaloor Village attained a laying progress of 12%, temporary stopped For POOTHAKULAM grama Panchayat - 14.7 km laid out of 32.56 km and for paravoor 7.4km laid out of 17.16 km Kollam Project HD
13 Jun 2021 Work stopped due to Lock down restrictions and some of the labours tested COVID 19- positive, KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46% - interconnection works in progress...Package 2 Pooyapally Village attained a laying progress of 100%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 48%, Package 7 Adichanaloor Village attained a laying progress of 12%, temporary stopped For POOTHAKULAM grama Panchayat - 14.7 km laid out of 32.56 km and for paravoor 7.4km laid out of 17.16 km Kollam Project HD
02 Jun 2021 Work stopped due to Lock down restrictions and some of the labours tested COVID 19- positive, KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46% - interconnection works in progress...Package 2 Pooyapally Village attained a laying progress of 100%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 48%, Package 7 Adichanaloor Village attained a laying progress of 12%, temporary stopped For POOTHAKULAM grama Panchayat - 14.7 km laid out of 32.56 km and for paravoor 7.4km laid out of 17.16 km Kollam Project HD
23 May 2021 Work stopped due to Lock down restrictions and some of the labours tested COVID 19- positive, KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46% - interconnection works in progress...Package 2 Pooyapally Village attained a laying progress of 100%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 48%, Package 7 Adichanaloor Village attained a laying progress of 12%, temporary stopped For POOTHAKULAM grama Panchayat - 14.7 km laid out of 32.56 km and for paravoor 7.4km laid out of 17.16 km Kollam Project HD
18 May 2021 Work stopped due to Lock down restrictions and some of the labours tested COVID 19- positive, KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46% - interconnection works in progress...Package 2 Pooyapally Village attained a laying progress of 100%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 48%, Package 7 Adichanaloor Village attained a laying progress of 12%, temporary stopped For POOTHAKULAM grama Panchayat - 14.7 km laid out of 32.56 km and for paravoor 7.4km laid out of 17.16 km Kollam Project HD
18 May 2021 The Corporation has informed that they will be able to provide police protection for the works on 11.05.2021 but postponed due to COVID 19 lock down restrictions by GOK. No Works started due to the above Kollam Project HD
13 May 2021 Work stopped due to Lock down restrictions and some of the labours tested COVID 19- positive, KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46% - interconnection works in progress...Package 2 Pooyapally Village attained a laying progress of 100%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 48%, Package 7 Adichanaloor Village attained a laying progress of 12%, temporary stopped For POOTHAKULAM grama Panchayat - 14.7 km laid out of 32.56 km and for paravoor 7.4km laid out of 17.16 km Kollam Project HD
10 May 2021 Work stopped due to Lock down restrictions and some of the labours tested COVID 19- positive, KIIFB -Chathoor drinking water project is tendered as 7 packages and all Packages are in progress.Package 1 Paravoor Muncipality attained a laying progress of 46% - interconnection works in progress...Package 2 Pooyapally Village attained a laying progress of 100%, Package 3 Meenad Village attained a laying progress of 100% ,Package 4 Chirakkara Village attained a laying progress of 100% ,Package 5 Paravoor Part Village attained a laying progress of 100% ,Package 6 Poothakulam Village attained a laying progress of 48%, Package 7 Adichanaloor Village attained a laying progress of 12%, temporary stopped For POOTHAKULAM grama Panchayat - 14.7 km laid out of 32.56 km and for paravoor 7.4km laid out of 17.16 km Kollam Project HD
10 May 2021 1Work stopped due to some of labours tested COVID 19 positive and due to lock down restrictions by GOK. 14.70 Km laid out of 32.56Km no work - Poothakulam grama panchayath is declared as COVID 19- Containment zone Kollam Project HD