Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
07 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
06 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
04 May 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
03 May 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
02 May 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
30 Apr 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
29 Apr 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
27 Apr 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
25 Apr 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE