Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
08 May 2024 | Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm | Thaliparamba WS Dn EE | |
07 May 2024 | Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm | Thaliparamba WS Dn EE | |
06 May 2024 | Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm | Thaliparamba WS Dn EE | |
04 May 2024 | 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm | Thaliparamba WS Dn EE | |
03 May 2024 | 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm | Thaliparamba WS Dn EE | |
02 May 2024 | 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm | Thaliparamba WS Dn EE | |
30 Apr 2024 | 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm | Thaliparamba WS Dn EE | |
29 Apr 2024 | 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm | Thaliparamba WS Dn EE | |
27 Apr 2024 | 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm | Thaliparamba WS Dn EE | |
25 Apr 2024 | 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm | Thaliparamba WS Dn EE |