Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
28 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
27 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
25 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
24 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
23 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
22 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
21 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
20 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
18 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE