Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
16 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
15 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
14 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
13 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
10 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
10 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
09 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
09 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
08 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE