Status Date Overall Project Status Project Officer Contact
02 Apr 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
01 Apr 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
30 Mar 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
27 Mar 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
26 Mar 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
25 Mar 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
23 Mar 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
22 Mar 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
21 Mar 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
22 Mar 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE