Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Jun 2024 Package 1 - Pipe partially supplied,8667 m pipe laid .Package 2 - Work completed and bill under preparation Thaliparamba WS Dn EE
17 Jun 2024 Package 1 - Pipe partially supplied,8667 m pipe laid .Package 2 - Work completed and bill under preparation Thaliparamba WS Dn EE
20 Jun 2024 Package 1 - Pipe partially supplied. Package 2-work completed and bill under preparation Thaliparamba WS Dn EE
19 Jun 2024 Package 1 - Pipe partially supplied. Package 2-work completed and bill under preparation Thaliparamba WS Dn EE
18 Jun 2024 Package 1 - Pipe partially supplied. Package 2-work completed and bill under preparation Thaliparamba WS Dn EE
18 Jun 2024 Work completed and bill under preparation Thaliparamba WS Dn EE
15 Jun 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
14 Jun 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
13 Jun 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
12 Jun 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE