Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
18 Jun 2024 | Package 1 - Pipe partially supplied,8667 m pipe laid .Package 2 - Work completed and bill under preparation | Thaliparamba WS Dn EE | |
17 Jun 2024 | Package 1 - Pipe partially supplied,8667 m pipe laid .Package 2 - Work completed and bill under preparation | Thaliparamba WS Dn EE | |
20 Jun 2024 | Package 1 - Pipe partially supplied. Package 2-work completed and bill under preparation | Thaliparamba WS Dn EE | |
19 Jun 2024 | Package 1 - Pipe partially supplied. Package 2-work completed and bill under preparation | Thaliparamba WS Dn EE | |
18 Jun 2024 | Package 1 - Pipe partially supplied. Package 2-work completed and bill under preparation | Thaliparamba WS Dn EE | |
18 Jun 2024 | Work completed and bill under preparation | Thaliparamba WS Dn EE | |
15 Jun 2024 | Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. | Thaliparamba WS Dn EE | |
14 Jun 2024 | Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. | Thaliparamba WS Dn EE | |
13 Jun 2024 | Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. | Thaliparamba WS Dn EE | |
12 Jun 2024 | Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. | Thaliparamba WS Dn EE |