Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Mar 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
07 Mar 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
06 Mar 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
05 Mar 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
04 Mar 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
02 Mar 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
01 Mar 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
29 Feb 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
28 Feb 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE
27 Feb 2024 1732 FHTC completed. Tenth and part bill submitted. Since pipes under project division and WS division are to be done in same trench,work is now held up due to delay in obtaining permission by Project division whoes trench size is for 700 mm and for WS is for 150 mm Thaliparamba WS Dn EE