Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Jun 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
10 Jun 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
07 Jun 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
06 Jun 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
05 Jun 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
04 Jun 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
03 Jun 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
01 Jun 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
31 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE
30 May 2024 Package 1 - Pipe partially supplied. Package 2-1732 FHTC completed. Tenth and part bill submitted. Out of the 700 m pumping main,646 m has been laid and 54 m remaining. Thaliparamba WS Dn EE