Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
28 Jun 2024 | Package 1 - Pipe partially supplied,8667 m pipe laid .Package 2 - Work completed and bill under preparation | Thaliparamba WS Dn EE | |
27 Jun 2024 | Package 1 - Pipe partially supplied,8667 m pipe laid .Package 2 - Work completed and bill under preparation | Thaliparamba WS Dn EE | |
26 Jun 2024 | Package 1 - Pipe partially supplied,8667 m pipe laid .Package 2 - Work completed and bill under preparation | Thaliparamba WS Dn EE | |
26 Jun 2024 | Site handed over to the contractor | Thaliparamba WS Dn EE | |
25 Jun 2024 | Package 1 - Pipe partially supplied,8667 m pipe laid .Package 2 - Work completed and bill under preparation | Thaliparamba WS Dn EE | |
24 Jun 2024 | Package 1 - Pipe partially supplied,8667 m pipe laid .Package 2 - Work completed and bill under preparation | Thaliparamba WS Dn EE | |
22 Jun 2024 | Package 1 - Pipe partially supplied,8667 m pipe laid .Package 2 - Work completed and bill under preparation | Thaliparamba WS Dn EE | |
21 Jun 2024 | Package 1 - Pipe partially supplied,8667 m pipe laid .Package 2 - Work completed and bill under preparation | Thaliparamba WS Dn EE | |
20 Jun 2024 | Package 1 - Pipe partially supplied,8667 m pipe laid .Package 2 - Work completed and bill under preparation | Thaliparamba WS Dn EE | |
19 Jun 2024 | Package 1 - Pipe partially supplied,8667 m pipe laid .Package 2 - Work completed and bill under preparation | Thaliparamba WS Dn EE |