Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Nov 2022 PACK-1 -completed ON 30.09.2021, pack-2-completed on 31.05.2021 ,PACK-3-THIS WORK WILL BE ARRANGED UNDER JAL JEEVAN MISSION. Chittur Project Dn - AE 1
07 Aug 2022 PACK-1 -completed,pack-2-completed,PACK-3-Not Started | 24/07/2022Permissive sanction for land obtained on 23.06.2022, vide order No: DCPKD/778/2022-LRG2 dtd 23.06.2022, HENCE THIS WORK WILL BE ARRANGED UNDER JAL JEEVAN MISSION. LETTER SUBMITTED TO NSS ENGINEERING COLLEGE, PALAKKAD FOR SOIL INVESTIGATION Chittur Project Dn - AE 1
31 Jul 2022 Not Started | 24/07/2022Permissive sanction for land obtained on 23.06.2022, vide order No: DCPKD/778/2022-LRG2 dtd 23.06.2022, HENCE THIS WORK WILL BE ARRANGED UNDER JAL JEEVAN MISSION. LETTER SUBMITTED TO NSS ENGINEERING COLLEGE, PALAKKAD FOR SOIL INVESTIGATION Chittur Project Dn - AE 1
24 Jul 2022 Not Started | 24/07/2022Permissive sanction for land obtained on 23.06.2022, vide order No: DCPKD/778/2022-LRG2 dtd 23.06.2022, HENCE THIS WORK WILL BE ARRANGED UNDER JAL JEEVAN MISSION. LETTER SUBMITTED TO NSS ENGINEERING COLLEGE, PALAKKAD FOR SOIL INVESTIGATION Chittur Project Dn - AE 1
19 Jul 2022 Not Started | 15/07/2022 Permissive sanction for land obtained on 23.06.2022, vide order No: DCPKD/778/2022-LRG2 dtd 23.06.2022,THIS WORK ARRANGED UNDER JALJEEVAN MISSION, ESTIMATE SUBMITTED FOR APPROVAL Chittur Project Dn - AE 1
15 Jul 2022 Not Started | 15/07/2022 Permissive sanction for land obtained on 23.06.2022, vide order No: DCPKD/778/2022-LRG2 dtd 23.06.2022,THIS WORK ARRANGED UNDER JALJEEVAN MISSION, ESTIMATE SUBMITTED FOR APPROVAL Chittur Project Dn - AE 1
10 Jul 2022 Not Started | 10/07/2022 Permissive sanction for land obtained on 23.06.2022, vide order PACK-III, No: DCPKD/778/2022-LRG2 dtd 23.06.2022,THIS WORK ARRANGED UNDER JALJEEVAN MISSION, ESTIMATE SUBMITTED FOR APPROVAL Chittur Project Dn - AE 1
07 Jul 2022 Not Started | 07/07/2022 PACK-III Permissive sanction for land obtained on 23.06.2022, vide order No: DCPKD/778/2022-LRG2 dtd 23.06.2022,THIS WORK ARRANGED UNDER JALJEEVAN MISSION Chittur Project Dn - AE 1
27 Jun 2022 Not Started | 27/06/2022pack-3Permissive sanction for land obtained from District collector palakkad ( present-Mrinmayi joshi,IAS) on 23.06.2022, vide order No: DCPKD/778/2022-LRG2 dtd 23.06.2022 Chittur Project Dn - AE 1
23 Jun 2022 PACK-I Work has been completed | 100% Completed |23/6/2022 Work completed on 30.9.2021 PACK-2 Work has been completed | 100% Completed |23/6/2022 -work completed on 31.5.2021. balance Bill under preparation Pack-III-Not Started |23/6/2022 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound Chittur Project Dn - AE 1