Status Date |
Overall Project Status |
Project Officer |
Contact |
13 Apr 2021 |
Package-I
Work in progress | 87% Completed | 13/04/2021
kockikkad-5 LL Kochikkad tank-sidewall second lift concrete work complete balance work in progress chamiyarkalam tank-linking work also progress
PACKAGE-II
Work in progress | 81% Completed | 13/04/2021
As per the direction of the District collector Proceeding No.E4-2021/234814/9 dated 16/03/2021 in connection with the General Election to Kerala LAC 2021.As per the direction contractor has resume the work only after 07.04.2021.Also there is delay in getting bittumin and the levels is to be get approved. The time allowed for completing the work expires on 31.03.2021. The contractor has request to allow time extentention up to 31.05.2021 to complete the work.
|
Chittur Project Dn - AE 1 |
|
07 Apr 2021 |
Package-1
Work in progress | 87% Completed | 07/04/2021
Haunch concrete work completed and balance work in progress at Kochikkad OHSR, Chamiyarkalam tank site- charging partialy-Street tap pressure from Chamiyarkalam tank ( kannimary to Ayyappankavu ) . linking work also progressing
Package-2
Work in progress | 81% Completed | 07/04/2021
As per the direction of the District collector Proceeding No.E4-2021/234814/9 dated 16/03/2021 in connection with the General Election to Kerala LAC 2021.As per the direction contractor has resume the work only after 07.04.2021.Also there is delay in getting bittumin and the levels is to be get approved. The time allowed for completing the work expires on 31.03.2021. The contractor has request to allow time extentention up to 15.05.2021 to complete the work.
|
Chittur Project Dn - AE 1 |
|
31 Mar 2021 |
package-1-87% of work complete
Water reached at 17.5 LL Ohsr chamiyarkalam, and clamp fixing work progressing at kk pathy bridge,kochikkad 5LL OHSR-FLOOR slab and beam concrete work completed
package-2-81% OF WORK COMPLETE
fixing identification block work proressing
|
Chittur Project Dn - AE 1 |
|
29 Mar 2021 |
Package-1
Work in progress | 86% Completed | 29/03/2021
350mm DI pipe gapl filling (laying work) and linking works are in progress
Package-2
Work in progress | 81% Completed | 29/03/2021
Identification block fixing work also progressing
|
Chittur Project Dn - AE 1 |
|
27 Mar 2021 |
Package-1
Work in progress | 86% Completed | 27/03/2021
Ms pipe laying work progress at kk pathy bridge, Anchor block 350 mm pumping main for chamiyarkalam tank near kk pathy plant ,350mm di pipe laying progress at kk pathy bridge, 16 LL OHSR at kanakkanpara. Inside plastering work in progress, column pipes, NRV supplied Air valve fixing 350 mm pumping main for Chamiyarkalam tank
Package-2
Work in progress | 81% Completed
Identification block fixing work also progressing
|
Chittur Project Dn - AE 1 |
|
24 Mar 2021 |
Package-I
Work in progress | 85% Completed | 24/03/2021
5 LL tank - Flòor beam and slab reinforcement work in progress at Kochikkad tank 16.00 LL -Walkway plastering work in progress at Kanakkanpara 16 LL OHSR 17.50 LL –PAINTING WORK ALMOST COMPLETE kk pathy bridge work progressing
Package-II
Work in progress | 81% Completed | 24/03/2021
pipe line work completed , BMBC- balance Road restoration work progressing
|
Chittur Project Dn - AE 1 |
|
18 Mar 2021 |
package-1
kk pathy bridge work in progress, OHSR s plastering work progress
package-2
Work in progress | 81% Completed | 18/03/2021
PALAKKAD POLLACHI ROAD WORK -(GSB)-progressing
|
Chittur Project Dn - AE 1 |
|
17 Mar 2021 |
Package-I
Work in progress | 85% Completed | 17/03/2021
5 LL kochikkad tank-floor beam reinforcement work in progress. 350 DI K9 pipe Gap linking work in progress ,bridge work in progress
Package-II
Work in progress | 81% Completed | 17/03/2021
PALAKKAD POLLACHI ROAD WORK -(GSB)started
|
Chittur Project Dn - AE 1 |
|
16 Mar 2021 |
Work in progress | 84% Completed | 16/03/2021
PACKAGE-1
1. Chequered plate laying work in progress at kk pathy bridge
2. 400 mm DI pipe laying in progress at mettukkada for kanakkanpara pumping main ( balance )
3. Walkway plastering work in progress at Kanakkanpara 16 LL OHSR
17.5 LL OHSR at chamiyarkalam colourwashing is in progress.
Chamiyarkalam tank compound wall plastering in progress kk pathy bridge work progressing
16LL- OHSR- coverslab handrail work is in progress Kanakkanpara ohsr coverslab curing work also progressing,outside plastering work started.
kochikkad-5LL -OHSR-floor slab and beam shuttering and reinforcement work progressing ,
PACKAGE-2
Work in progress | 81% Completed | 16/03/2021
balance Road restoration work to be started
|
Chittur Project Dn - AE 1 |
|
12 Mar 2021 |
Package-1
Work in progress | 84% Completed | 12/03/2021
17.5 LL OHSR at chamiyarkalam colourwashing is in progress. Chamiyarkalam tank compound wall plastering in progress kk pathy bridge work progressing 16LL- OHSR- coverslab handrail work is in progress Kanakkanpara ohsr coverslab curing work also progressing,outside plastering work started. kochikkad-5LL -OHSR-floor slab and beam shuttering and reinforcement work progressing ,
Package-2
Work in progress/81% completed/12/3/2021
Third and part bill prepared for an amount of Rs. 57.27827 Lakhs. (AE submit)
Work intimation report -1 (form No. KIIFB (IAT)-1 submitted to The Chief Project Examiner ,Thiruvananthapuram. BMBC- balance Road restoration work to be started
|
Chittur Project Dn - AE 1 |
|