Status Date |
Overall Project Status |
Project Officer |
Contact |
13 Feb 2022 |
PACK-I Work has been completed | 100% Completed |13/2/2022 Work completed on 30.9.2021 PACK-2 Work has been completed | 100% Completed |13/2/2022 BM BC -Road restoration work completed,pipe line laying work completed-work completed on 31.5.2021. balance Bill under preparation Pack-III-Not Started |13/02/2022 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound |
Chittur Project Dn - AE 1 |
|
06 Feb 2022 |
PACK-I Work has been completed | 100% Completed |06/2/2022 Work completed on 30.9.2021 PACK-2 Work has been completed | 100% Completed |06/2/2022 BM BC -Road restoration work completed,pipe line laying work completed-work completed on 31.5.2021. balance Bill under preparation Pack-III-Not Started |06/02/2022 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound |
Chittur Project Dn - AE 1 |
|
31 Jan 2022 |
PACK-I Work has been completed | 100% Completed |31/1/2022 Work completed on 30.9.2021 PACK-2 Work has been completed | 100% Completed |34/1/2022 BM BC -Road restoration work completed,pipe line laying work completed-work completed on 31.5.2021. balance Bill under preparation Pack-III-Not Started |34/01/2022 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound |
Chittur Project Dn - AE 1 |
|
24 Jan 2022 |
PACK-I Work has been completed | 100% Completed |24/1/2022 Work completed on 30.9.2021 PACK-2 Work has been completed | 100% Completed |24/1/2022 BM BC -Road restoration work completed,pipe line laying work completed-work completed on 31.5.2021. balance Bill under preparation Pack-III-Not Started |24/01/2022 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound |
Chittur Project Dn - AE 1 |
|
20 Jan 2022 |
PACK-I Work has been completed | 100% Completed |20/1/2022 Work completed on 30.9.2021 PACK-2 Work has been completed | 100% Completed |20/1/2022 BM BC -Road restoration work completed,pipe line laying work completed-work completed on 31.5.2021. balance Bill under preparation Pack-III-Not Started |20/01/2022 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound |
Chittur Project Dn - AE 1 |
|
13 Jan 2022 |
PACK-I Work has been completed | 100% Completed |13/1/2022 Work completed on 30.9.2021 PACK-2 Work has been completed | 100% Completed |13/1/2022 BM BC -Road restoration work completed,pipe line laying work completed-work completed on 31.5.2021. balance Bill under preparation Pack-III-Not Started |13/01/2022 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound |
Chittur Project Dn - AE 1 |
|
10 Jan 2022 |
PACK-I Work has been completed | 100% Completed |10/1/2022 Work completed on 30.9.2021 PACK-2 Work has been completed | 100% Completed |10/1/2022 BM BC -Road restoration work completed,pipe line laying work completed-work completed on 31.5.2021. balance Bill under preparation Pack-III-Not Started |10/01/2022 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound |
Chittur Project Dn - AE 1 |
|
05 Jan 2022 |
PACK-I Work has been completed | 100% Completed |05/1/2022 Work completed on 30.9.2021 PACK-2 Work has been completed | 100% Completed |05/1/2022 BM BC -Road restoration work completed,pipe line laying work completed-work completed on 31.5.2021. balance Bill under preparation Pack-III-Not Started | 05/01/2022 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound |
Chittur Project Dn - AE 1 |
|
02 Jan 2022 |
PACK-I
Work has been completed | 100% Completed | 31/12/2021
Work completed on 30.9.2021
PACK-2
Work has been completed | 100% Completed | 31/12/2021
BM BC -Road restoration work completed,pipe line laying work completed-work completed on 31.5.2021. balance Bill under preparation
Pack-III-Not Started | 02/01/2022
Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound
|
Chittur Project Dn - AE 1 |
|
31 Dec 2021 |
Pack-1
Work has been completed | 100% Completed | 31/12/2021
Work completed on 30.9.2021
Pack-3
Not Started | 31/12/2021
Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound
Pack-2
Work has been completed | 100% Completed | 31/12/2021
BM BC -Road restoration work completed,pipe line laying work completed-work completed on 31.5.2021. balance Bill under preparation
|
Chittur Project Dn - AE 1 |
|