Status Date |
Overall Project Status |
Project Officer |
Contact |
07 Nov 2021 |
pack-1 and 2 work completed,pack-3Not Started | 07/11/2021
Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound |
Chittur Project Dn - AE 1 |
|
31 Oct 2021 |
pack-1 and II -Work
completed
pack--III-Not Started | 31/10/2021
Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound |
Chittur Project Dn - AE 1 |
|
24 Oct 2021 |
Not Started | 24/10/2021
pack-1and 2 -work complete
Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound |
Chittur Project Dn - AE 1 |
|
24 Oct 2021 |
Not Started | 24/10/2021
Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound |
Chittur Project Dn - AE 1 |
|
17 Oct 2021 |
Pack-3
Started | 17/10/2021
Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound
Pack-1
Work completed on 30.9.2021
Pack-2
Work complete
|
Chittur Project Dn - AE 1 |
|
10 Oct 2021 |
pack-1
Work in progress | 95% Completed | 10/10/2021
95% of work almost completed.tank works completed
pack-2
work completed
pack-3
work not started |
Chittur Project Dn - AE 1 |
|
02 Oct 2021 |
Pack-1
Work in progress | 95% Completed | 02/10/2021
1.) Kochikkad 5LL OHSR in Pattanchery panchayath- Compound wall Plastering work complete 2.) 17.50LL OHSR-Chamiyarkalam - Earth filling completed Road crossing restoration work at Kambalathara road complete
Pack-2
Work complete
Pack-3
Not Started | 02/10/2021
Not Started | 27/09/2021 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound
|
Chittur Project Dn - AE 1 |
|
27 Sep 2021 |
Pack-1
Work in progress | 95% Completed | 27/09/2021
1.) Kochikkad 5LL OHSR in Pattanchery panchayath- Compound wall Plastering work and gate work in progress 2.) 17.50LL OHSR-Chamiyarkalam - Earth filling completed
Pack-2
Work complete
Pack-3
Not Started | 27/09/2021
Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound
|
Chittur Project Dn - AE 1 |
|
24 Sep 2021 |
Pack-1
Work in progress | 95% Completed | 24/09/2021
1.) Kochikkad 5LL OHSR in Pattanchery panchayath- Compound wall Plastering work and gate work in progress 2.) 17.50LL OHSR-Chamiyarkalam - Earth filling completed
Pack-2
Work completed
Pack-3
Not Started | 24/09/2021
Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound
|
Chittur Project Dn - AE 1 |
|
20 Sep 2021 |
Pack-1
Work in progress | 95% Completed | 20/09/2021
Laying 250mm CW PM to kochikkad ohsr & column pipe work in progress. 1). KOCHIKKAD -painting work in progress 2). kanakkanpara tank-compound wall work in progress
Pack-2-work complete
Pack-3
Not Started | 20/09/2021
Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound
|
Chittur Project Dn - AE 1 |
|