Status Date |
Overall Project Status |
Project Officer |
Contact |
14 Sep 2021 |
Pack-1
Work in progress | 95% Completed | 14/09/2021
Laying 250mm CW PM to kochikkad ohsr & 350mm distribution main from kochikkad ohsr, column pipe works also progress. 1). KOCHIKKAD -painting work in progress 2). kanakkanpara tank-compound wall work in progress
Pack-2-
work completed
Pack-3
Not Started | 14/09/2021
Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound
|
Chittur Project Dn - AE 1 |
|
09 Sep 2021 |
Pack-1
Work in progress | 95% Completed | 09/09/2021
Laying 250mm CW PM to kochikkad ohsr & column pipe work in progress. 1). KOCHIKKAD -painting work in progress 2). kanakkanpara tank-compound wall work in progress
Pack-2
Work complete
Pack-3
Not Started | 09/09/2021
Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound
|
Chittur Project Dn - AE 1 |
|
04 Sep 2021 |
Pack-1
Work in progress | 95% Completed | 04/09/2021
1). KOCHIKKAD -painting work in progress 2). kanakkanpara tank-compound wall work in progress
Pcak-2
Work complete
Pack-3
Not Started | 04/09/2021
Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound
|
Chittur Project Dn - AE 1 |
|
29 Aug 2021 |
Pack-I
Work in progress | 95% Completed | 29/08/2021
1). KOCHIKKAD -painting work in progress 2). kanakkanpara tank-compound wall work in progress
PACK-2
WORK Complete
Pack-3
Not Started | 29/08/2021
Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound
|
Chittur Project Dn - AE 1 |
|
16 Aug 2021 |
Pack-1
Work in progress | 95% Completed | 16/08/2021
KOCHIKKAD -plastering work completed and whitewashing work in progress
Pack-2
Work completed
Pack-3
Not Started | 16/08/2021
Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound
|
Chittur Project Dn - AE 1 |
|
09 Aug 2021 |
Pack-I
Work in progress | 95% Completed | 09/08/2021
plastering work in progressing AT KOCHIKKAD tank site
pack-2
work completed
pack-3
Not Started | 09/08/2021
Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound
|
Chittur Project Dn - AE 1 |
|
01 Aug 2021 |
Pack-1
Work in progress | 95% Completed | 01/08/2021
Lintel and sunshade concrete work complete at Kochikkad OHSR plastering work also progressing
Pack-2
Work complete
Pack-3
Not Started | 01/08/2021
Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound
|
Chittur Project Dn - AE 1 |
|
27 Jul 2021 |
Pack-1
Work in progress | 95% Completed | 27/07/2021
Lintel and sunshade concrete in progressing at Kochikkad OHSR
Pack-2
Work complete
Pack-3
Not Started | 27/07/2021
Not Started | 24/07/2021 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound
|
Chittur Project Dn - AE 1 |
|
24 Jul 2021 |
Pack-1
Work in progress | 95% Completed | 24/07/2021
Handrail work in progress and Floor plastering completed at Kochikkad OHSR
Pack-2
Work complete
Pack-3
Not Started | 24/07/2021
Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound
|
Chittur Project Dn - AE 1 |
|
19 Jul 2021 |
Pack-1
Work in progress | 95% Completed | 19/07/2021
Handrail work in progress and Floor plastering completed at Kochikkad OHSR
Pack-2
Completed
Pack-3
Not Started | 19/07/2021
Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound
|
Chittur Project Dn - AE 1 |
|