Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Sep 2021 Pack-1 Work in progress | 95% Completed | 14/09/2021 Laying 250mm CW PM to kochikkad ohsr & 350mm distribution main from kochikkad ohsr, column pipe works also progress. 1). KOCHIKKAD -painting work in progress 2). kanakkanpara tank-compound wall work in progress Pack-2- work completed Pack-3 Not Started | 14/09/2021 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound Chittur Project Dn - AE 1
09 Sep 2021 Pack-1 Work in progress | 95% Completed | 09/09/2021 Laying 250mm CW PM to kochikkad ohsr & column pipe work in progress. 1). KOCHIKKAD -painting work in progress 2). kanakkanpara tank-compound wall work in progress Pack-2 Work complete Pack-3 Not Started | 09/09/2021 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound Chittur Project Dn - AE 1
04 Sep 2021 Pack-1 Work in progress | 95% Completed | 04/09/2021 1). KOCHIKKAD -painting work in progress 2). kanakkanpara tank-compound wall work in progress Pcak-2 Work complete Pack-3 Not Started | 04/09/2021 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound Chittur Project Dn - AE 1
29 Aug 2021 Pack-I Work in progress | 95% Completed | 29/08/2021 1). KOCHIKKAD -painting work in progress 2). kanakkanpara tank-compound wall work in progress PACK-2 WORK Complete Pack-3 Not Started | 29/08/2021 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound Chittur Project Dn - AE 1
16 Aug 2021 Pack-1 Work in progress | 95% Completed | 16/08/2021 KOCHIKKAD -plastering work completed and whitewashing work in progress Pack-2 Work completed Pack-3 Not Started | 16/08/2021 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound Chittur Project Dn - AE 1
09 Aug 2021 Pack-I Work in progress | 95% Completed | 09/08/2021 plastering work in progressing AT KOCHIKKAD tank site pack-2 work completed pack-3 Not Started | 09/08/2021 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound Chittur Project Dn - AE 1
01 Aug 2021 Pack-1 Work in progress | 95% Completed | 01/08/2021 Lintel and sunshade concrete work complete at Kochikkad OHSR plastering work also progressing Pack-2 Work complete Pack-3 Not Started | 01/08/2021 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound Chittur Project Dn - AE 1
27 Jul 2021 Pack-1 Work in progress | 95% Completed | 27/07/2021 Lintel and sunshade concrete in progressing at Kochikkad OHSR Pack-2 Work complete Pack-3 Not Started | 27/07/2021 Not Started | 24/07/2021 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound Chittur Project Dn - AE 1
24 Jul 2021 Pack-1 Work in progress | 95% Completed | 24/07/2021 Handrail work in progress and Floor plastering completed at Kochikkad OHSR Pack-2 Work complete Pack-3 Not Started | 24/07/2021 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound Chittur Project Dn - AE 1
19 Jul 2021 Pack-1 Work in progress | 95% Completed | 19/07/2021 Handrail work in progress and Floor plastering completed at Kochikkad OHSR Pack-2 Completed Pack-3 Not Started | 19/07/2021 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound Chittur Project Dn - AE 1