Status Date |
Overall Project Status |
Project Officer |
Contact |
25 May 2021 |
Package-1
Work in progress | 93% Completed | 25/05/2021
kanakkanpara tank site-plastering work and painting works are in progress
package-2
Work in progress | 85% Completed | 25/05/2021
BMBC work started-(palakkad-pollachi road)
|
Chittur Project Dn - AE 1 |
|
19 May 2021 |
Package-1
Work in progress | 90% Completed | 19/05/2021
kanakkanpara tank site-plastering work and painting works are in progress
Package-2
Work in progress | 81% Completed | 19/05/2021
Work intimation report( CTE REPORT) -2 (form No. KIIFB (IAT)-1 submitted to The Chief Project Examiner , Thiruvananthapuram. BMBC- balance Road restoration work to be started
|
Chittur Project Dn - AE 1 |
|
14 May 2021 |
Package-1 Work in progress | 89% Completed | 14/05/2021 1.kankkan para 16 LL OHSR-Plastering work progress 2. kochikkad-5LL OHSR-Cover slab curing work progress and staircase concrete Work in progress
Package-2 Work intimation report( CTE REPORT) -2 (form No. KIIFB (IAT)-1 submitted to The Chief Project Examiner , Thiruvananthapuram. BMBC- balance Road restoration work to be started |
Chittur Project Dn - AE 1 |
|
11 May 2021 |
Package-1
Work in progress | 89% Completed | 11/05/2021
1.kankkan para 16 LL OHSR-Plastering work progress 2. kochikkad-5LL OHSR-Cover slab curing work progress
Package-2
Work intimation report( CTE REPORT) -2 (form No. KIIFB (IAT)-1 submitted to The Chief Project Examiner , Thiruvananthapuram. BMBC- balance Road restoration work to be started
|
Chittur Project Dn - AE 1 |
|
05 May 2021 |
Package-1
Work in progress | 88% Completed | 05/05/2021
5LL KOchikkad tank site-cover slab concrete work complete. Curing also progressing
Package-2
Work in progress | 81% Completed | 05/05/2021
Road restoration balance work to be completed.Third time extension granted up to 31.05.2021 vide order no.KWA/PHC/PKD/KIIFB/ELAPPULLY/PHASE-II/pkg II dtd 12.04.20211
|
Chittur Project Dn - AE 1 |
|
29 Apr 2021 |
Package-I
Work in progress | 88% Completed | 29/04/2021
16 LL OHSR at kanakkanpara washing completed & pumping started, 350 mm Gravity main to elapully charging work start
Package-II
Work in progress | 81% Completed | 29/04/2021
Road restoration balance work to be completed.Third time extension granted up to 31.05.2021 vide order no.KWA/PHC/PKD/KIIFB/ELAPPULLY/PHASE-II/pkg II dtd 12.04.20211
|
Chittur Project Dn - AE 1 |
|
26 Apr 2021 |
Package-I
Work in progress | 88% Completed | 26/04/2021
16 LL OHSR at kanakkanpara washing completed & pumping started, 350 mm Gravity main to elapully charging work started.
package-II
Work in progress | 81% Completed | 26/04/2021
Road restoration balance work to be completed.Third time extension granted up to 31.05.2021 vide order no.KWA/PHC/PKD/KIIFB/ELAPPULLY/PHASE-II/pkg II dtd 12.04.20211
|
Chittur Project Dn - AE 1 |
|
20 Apr 2021 |
Package-I
. Work in progress | 87% Completed | 20/04/2021
1) .400mm DI Kanakkampara pumping main bridge crossing at Kkpathy -work in progress 2) Side wall last lift concrete work complete at Kochikkad 5LL OHSR 3)400x90 DI Bend concrete work progress at bridge crossing KKpathy
Package-II
Work in progress | 81% Completed | 20/04/2021
Road restoration balance work to be completed.Third time extension granted up to 31.05.2021 vide order no.KWA/PHC/PKD/KIIFB/ELAPPULLY/PHASE-II/pkg II dtd 12.04.20211
|
Chittur Project Dn - AE 1 |
|
19 Apr 2021 |
Package-I
Work in progress | 87% Completed | 19/04/2021
1. Side wall last lift concrete progressing at Kochikkad 5LL OHSR 2. 400x90 DI Bend concrete work progress at bridge crossing KKpathy
Package-II
Work in progress | 81% Completed | 19/04/2021
Work in progress | 81% Completed | 13/04/2021 As per the direction of the District collector Proceeding No.E4-2021/234814/9 dated 16/03/2021 in connection with the General Election to Kerala LAC 2021.As per the direction contractor has resume the work only after 07.04.2021.Also there is delay in getting bittumin and the levels is to be get approved. The time allowed for completing the work expires on 31.03.2021. The contractor has request to allow time extentention up to 31.05.2021 to complete the work.
|
Chittur Project Dn - AE 1 |
|
15 Apr 2021 |
Work in progress | 87% Completed | 15/04/2021
kockikkad-5 LL Kochikkad tank-sidewall second lift concrete work complete and third lift shuttering work in progress
package-II
BMBC work balance |
Chittur Project Dn - AE 1 |
|