Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Jul 2021 Pack-1 Work in progress | 95% Completed | 12/07/2021 kanakkanpara tank site-colour washing works are in progress, kochikkad tank plastering work in progress. Pack-2 Work has been completed | 100% Completed | 31/05/2021 Pack-3 Not Started | 09/07/2021 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound Chittur Project Dn - AE 1
09 Jul 2021 Pack-1 Work in progress | 95% Completed | 09/07/2021 kanakkanpara tank site-colour washing works are in progress, kochikkad tank plastering work in progress. Pack-2 Work has been completed | 100% Completed | 31/05/2021 Pack-3 Not Started | 09/07/2021 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound Chittur Project Dn - AE 1
03 Jul 2021 PACKAGE 1 Work in progress | 95% Completed | 03/07/2021 kanakkanpara tank site-colour washing works are in progress, kochikkad tank plastering work in progress. PACKAGE 2 Work complete. Final will under preparation PACKAGE 3 Not Started | 03/07/2021 Work not started Chittur Project Dn - AE 1
28 Jun 2021 pack-1-Work in progress | 95% Completed | 28/06/2021 kanakkanpara tank site-colour washing works are in progress, kochikkad tank plastering work in progress. pack-2- work completed Chittur Project Dn - AE 1
20 Jun 2021 pack-1 tank site-colour washing works are in progress, kochikkad tank plastering work in progress. Chittur Project Dn - AE 1
16 Jun 2021 Pack-1 Work in progress | 95% Completed | 16/06/2021 kanakkanpara tank site-colour washing works are in progress, kochikkad tank plastering work in progress. Pack-2 Work has been completed | 100% Completed | 31/05/2021 BM BC -Road restoration work completed,pipe line laying work completed-work completed on 31.5.2021. balance Bill under preparation Chittur Project Dn - AE 1
14 Jun 2021 Package-1 Work in progress | 95% Completed | 14/06/2021 kanakkanpara tank site-colour washing works are in progress, kochikkad tank plastering work in progress. Package-2 Work in progress | 100% Completed | 14/06/2021 BM BC -Road restoration work completed, pipe line laying work completed-work completed on 31.5.2021. balance Bill prepared for Rs. 153,91,257.00 Chittur Project Dn - AE 1
08 Jun 2021 Work in progress | 95% Completed | 08/06/2021 kanakkanpara tank site-plastering work and painting works are in progress, kochikkad tank plastering work in progress. Work has been completed | 100% Completed | 31/05/2021 BM BC -Road restoration work completed,pipe line laying work completed-work completed on 31.5.2021. balance Bill under preparation Chittur Project Dn - AE 1
01 Jun 2021 Package-1 Work in progress | 94% Completed | 01/06/2021 kanakkanpara tank site-plastering work and painting works are in progress pack-2 Work has been completed | 100% Completed | 31/05/2021 BM BC -Road restoration work completed,pipe line laying work completed-work completed on 31.5.2021. balance Bill under preparation Chittur Project Dn - AE 1
27 May 2021 Work in progress | 93% Completed | 27/05/2021 kanakkanpara tank site-plastering work and painting works are in progress package-2 Work in progress | 86% Completed | 27/05/2021 BMBC -road restoration work is progressing -(palakkad-pollachi road) Chittur Project Dn - AE 1