Status Date |
Overall Project Status |
Project Officer |
Contact |
11 Jul 2021 |
Pack-1 Work in progress | 95% Completed | 12/07/2021 kanakkanpara tank site-colour washing works are in progress, kochikkad tank plastering work in progress. Pack-2 Work has been completed | 100% Completed | 31/05/2021 Pack-3 Not Started | 09/07/2021 Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound |
Chittur Project Dn - AE 1 |
|
09 Jul 2021 |
Pack-1
Work in progress | 95% Completed | 09/07/2021
kanakkanpara tank site-colour washing works are in progress, kochikkad tank plastering work in progress.
Pack-2
Work has been completed | 100% Completed | 31/05/2021
Pack-3
Not Started | 09/07/2021
Permissive sanction for land to be obtained from Animal Husbandry department for the construction of OHSR inside the Elappully Vetinary hospital compound
|
Chittur Project Dn - AE 1 |
|
03 Jul 2021 |
PACKAGE 1
Work in progress | 95% Completed | 03/07/2021
kanakkanpara tank site-colour washing works are in progress, kochikkad tank plastering work in progress.
PACKAGE 2
Work complete. Final will under preparation
PACKAGE 3
Not Started | 03/07/2021
Work not started
|
Chittur Project Dn - AE 1 |
|
28 Jun 2021 |
pack-1-Work in progress | 95% Completed | 28/06/2021
kanakkanpara tank site-colour washing works are in progress, kochikkad tank plastering work in progress.
pack-2- work completed |
Chittur Project Dn - AE 1 |
|
20 Jun 2021 |
pack-1
tank site-colour washing works are in progress, kochikkad tank plastering work in progress. |
Chittur Project Dn - AE 1 |
|
16 Jun 2021 |
Pack-1
Work in progress | 95% Completed | 16/06/2021
kanakkanpara tank site-colour washing works are in progress, kochikkad tank plastering work in progress.
Pack-2
Work has been completed | 100% Completed | 31/05/2021
BM BC -Road restoration work completed,pipe line laying work completed-work completed on 31.5.2021. balance Bill under preparation
|
Chittur Project Dn - AE 1 |
|
14 Jun 2021 |
Package-1
Work in progress | 95% Completed | 14/06/2021
kanakkanpara tank site-colour washing works are in progress, kochikkad tank plastering work in progress.
Package-2
Work in progress | 100% Completed | 14/06/2021
BM BC -Road restoration work completed, pipe line laying work completed-work completed on 31.5.2021. balance Bill prepared for Rs. 153,91,257.00
|
Chittur Project Dn - AE 1 |
|
08 Jun 2021 |
Work in progress | 95% Completed | 08/06/2021
kanakkanpara tank site-plastering work and painting works are in progress, kochikkad tank plastering work in progress.
Work has been completed | 100% Completed | 31/05/2021
BM BC -Road restoration work completed,pipe line laying work completed-work completed on 31.5.2021. balance Bill under preparation
|
Chittur Project Dn - AE 1 |
|
01 Jun 2021 |
Package-1
Work in progress | 94% Completed | 01/06/2021
kanakkanpara tank site-plastering work and painting works are in progress
pack-2
Work has been completed | 100% Completed | 31/05/2021
BM BC -Road restoration work completed,pipe line laying work completed-work completed on 31.5.2021. balance Bill under preparation
|
Chittur Project Dn - AE 1 |
|
27 May 2021 |
Work in progress | 93% Completed | 27/05/2021
kanakkanpara tank site-plastering work and painting works are in progress
package-2
Work in progress | 86% Completed | 27/05/2021
BMBC -road restoration work is progressing -(palakkad-pollachi road) |
Chittur Project Dn - AE 1 |
|