| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 22 Nov 2020 | Soil investigation completed on 19.11.2020 and a meeting is arranged with contactors by Superinting Engineer regarding working schedule and design part on 23.11.2020 | Kollam Project HD | |
| 12 Nov 2020 | Agreement executed on 28.10.2020 and as per the direction of Hon.collector and Mayor Kollam... Preliminary survey work started amongst high protest with police escort on 4.11.2020 ..land survey was completed on the same day itself ...On 10.11.2020 a tentative position for various structures were marked for soil investigation and soil investigation work started on 11.11.2020 with police protest and in progress | Kollam Project HD | |
| 01 Nov 2020 | A meeting was arranged at Sunbay Auditorium in the presence of Dist. Collector and Mayor Kollam to make aware to the public about the need of STP. The meeting started at 11.0 am as per the direction of Hon. Minister for Fisheries , and all the assembled party members, public expressed their positive support for the project after viewing the presentation about the need of sewerage treatment. The Hon. Collector as well as the Hon. Mayor, Kollam directed to go with the project by convincing public by giving proper awareness by all means and also to start the work urgently | Kollam Project HD | |
| 01 Nov 2020 | A meeting was arranged at Sunday Auditorium in the presence of Dist. Collector and Mayor Kollam to make aware to the public about the need of STP. The meeting started at 11.0 am as per the direction of Hon. Minister for Fisheries , and all the assembled party members, public expressed their positive support for the project after viewing the presentation about the need and advantages of sewerage treatment. The Him. Collector as well as the Hon. Mayor, Kollam directed to go with the project by convincing by giving proper awareness by all means and also to start the survey work urgently | Kollam Project HD | |
| 01 Nov 2020 | 20.10.2020 a meeting was convened in the presence of Hon. mayor, Kollam with protesters ,but no one agreed to even listening the presentation by KWA | Kollam Project HD | |
| 01 Nov 2020 | 15.10.2020 an all party meeting was organised at corporation office headed by Hon.Mayor and presented about the advantages and need of STP. | Kollam Project HD | |
| 01 Nov 2020 | 15.10.2020 an all party meeting was organised at corporation office headed by Hon.Mayor and presented about the advantages and need of STP. | Kollam Project HD | |
| 09 Sep 2020 | Letter from Dist.Collector on 27.07.2020, with the Instruction to start the work with the protection of Police. The Contractor has not signed the agreement with all relevant document till date.In this regard called the contractor and they agreed to came to the office on 11.09.2020. | Kollam Project HD | |
| 16 Aug 2020 | SE, Kollam conduct a meeting with STP contractors partner ABM from Eranakulam on 15.07.20217. The documents produced by them are not sufficient as per selection notice. The term period extend up to 31.08.2020 and they promised to do the agreement within the this period. SE,EE and AE met district collector and Hon. Minister of Fisheries and inform the public protest faced on site and given detailed report on 17.07.2020 to District collector as per direction. | Kollam Project HD | |
| 03 Jul 2020 | Today at 10.30am, water authority ae, Kollam corporation SE,EE, Amrut uint officers and Taluk surveyors team move to proposed 12mld stp Kureepuzha site for boundary fixing. The public gathered at site don't allow to proceed any work. On discussion with protesters corporation se and team decided to withdraw from site at 12.15pm. | AE6 JKLM |