24 Mar 2021 Work for survey and boundary demarcation by revenue -final survey and demarcation is scheduled on 25.03.2021 . For tree cutting , negotiation with the bidder in progress Kollam Project HD
22 Mar 2021 Work for survey and boundary demarcation by revenue in progress Kollam Project HD
20 Mar 2021 Demarcation of boundaries by Taluk surveyors in STP site in progress.. for tree cutting- As per the open auction conducted on 15.03.2021, only one participated and rate quoted is very low. So the bidder is called for negotiation by corporation office and process is under progress in revenue section Kollam Project HD
19 Mar 2021 Structural design for chlorine contact tank submitted for approval..As per the open auction conducted on 15.03.2021, only one participated and rate quoted is very low. So the bidder is called for negotiation by corporation office and process is under progress in revenue section Kollam Project HD
17 Mar 2021 As per the open auction conducted on 15.03.2021, only one participated and rate quoted is very low. So the bidder is called for negotiation by corporation office and process is under progress in revenue section Kollam Project HD
16 Mar 2021 As per the open auction conducted on 15.03.2021, only one participated and rate quoted is very low. So the bidder is called for negotiation by corporation office Kollam Project HD
12 Mar 2021 3 times auction conducted by the corporation Kollam...now Corporation revenue division decided to conduct open auction and notice published on 8.03.2021 ... With auction date 15.03.2021 and participation open upto 13.03.2021 Kollam Project HD
03 Mar 2021 Project Status Updation Update status Last updation Work in progress | 2% Completed | 02/03/2021 Work in delay due to tree cutting pending...3 times auction conducted by the corporation Kollam...but no offer obtained. The contractor requested for starting work by cutting trees and stack nearby with corporation permission. Proper decision will be taken by corporation committee dated 4.03.2021 Kollam Project HD
26 Feb 2021 no- offers submitted for -tree felling -for open submission dated - 25.02.2021 . contractor is ready for starting work MBBR tank ( structural design approved) but tree felling and boundary demarcation is pending Kollam Project HD
20 Feb 2021 No offers for tree felling auction...Notice for tree felling open offer reception notified by the Corporation Kollam.. structural design for MBBR approved by WASCON Kollam Project HD