| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 16 Feb 2021 | No bidders as per the auction notice by the corporation kollam. Time period extended with wide publicity to 7 more days up to 18.02.2021 with opening date on 19.02.2021. Tree felling to be done for progressing work | Kollam Project HD | |
| 05 Feb 2021 | Auction notice for tree felling published with 10.2.2021as submission date and 11.2.2021 with opening date... Soft copy of Structural design for 2 components on 3.02.2021 and hard copy submitted on 4.02.2021 and under scruitiny | Kollam Project HD | |
| 31 Jan 2021 | 8.01.2021..As discussed with corporation Kollam,assured that Tree cutting auction process as well as boundary darcation will do this week itself. Structural design will submit with in two days by the contractor | Kollam Project HD | |
| 29 Jan 2021 | 28.01.2021..As discussed with corporation Kollam,assured that Tree cutting auction process as well as boundary darcation will do this week itself. Structural design will submit with in two days by the contractor | Kollam Project HD | |
| 22 Jan 2021 | On 19.01.2021, the works for compound wall started and may be continued only after finalizing boundaries by the thaluk surveyor..The matter was discussed in the review meeting chaired by the Hon. Mayor Kollam. Meeting was ended with following discussions. 1. Permission for tree cutting will be finalised on next Tree committee dated 23.01.2021 2. Taluk surveyor/ Thalisdar was already intimated to do boundary demarcation urgently on disputed sides of the layout 3. The layout and process diagram was presented before PCB , and layout is permitted & approved 4.Directed contractor to submit structural drawings on or before 27.01.2021 and start the work | Kollam Project HD | |
| 22 Jan 2021 | n 12.01.2021, the site layout plan and hydraulic flow diagram approved and directed to submit structural design and to start compound wall works | Kollam Project HD | |
| 22 Jan 2021 | On 12.01.2020, the site layout plan and hydraulic flow diagram approved and directed to submit structural design and to start compound wall works | Kollam Project HD | |
| 10 Jan 2021 | on 6.01.2020- Layout and HFD submitted to WASCON for approval from SE' s office. | Kollam Project HD | |
| 05 Jan 2021 | Design in progress.. Layout submitted was directed to correct as per NIT conditions and directed to start compound wall works immediately. Tree committee for cutting trees & evaluation is on 8.1.2021 | Kollam Project HD | |
| 10 Dec 2020 | Design in progress.. layout submitted by the contractor on 10.12.2020 for approval in softcopy | Kollam Project HD |