18 Oct 2023 46.39 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -167 & HTC-461/2735 completed. Palakkad Proj AE 3
17 Oct 2023 46.39 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -167 & HTC-461/2735 completed. Palakkad Proj AE 3
16 Oct 2023 46.39 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -167 & HTC-461/2735 completed. Palakkad Proj AE 3
13 Oct 2023 45.58 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -167 & HTC-461/2735 completed. Palakkad Proj AE 3
12 Oct 2023 45.30 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -167 & HTC-461/2735 completed. Palakkad Proj AE 3
11 Oct 2023 45.12 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -167 & HTC-455/2735 completed. Palakkad Proj AE 3
10 Oct 2023 45.07 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -167 & HTC-455/2735 completed. Palakkad Proj AE 3
09 Oct 2023 45.07 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -160 & HTC-462/2735 completed. Palakkad Proj AE 3
07 Oct 2023 45.07 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -160 & HTC-460/2735 completed. Palakkad Proj AE 3
06 Oct 2023 45.07 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, progressing. FHTC -160 & HTC-460/2735 completed. Palakkad Proj AE 3