Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Sep 2023 40.62 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (487) & FHTC (124) progressing. Palakkad Proj AE 3
04 Sep 2023 40.46 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (477) & FHTC (124) progressing. Palakkad Proj AE 3
02 Sep 2023 40.46 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (477) & FHTC (124) progressing. Palakkad Proj AE 3
01 Sep 2023 40.46 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (477) & FHTC (124) progressing. Palakkad Proj AE 3
26 Aug 2023 40.46 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (477) & FHTC (124) progressing. Palakkad Proj AE 3
25 Aug 2023 40.46 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (477) & FHTC (124) progressing. Palakkad Proj AE 3
24 Aug 2023 40.39 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (464) & FHTC (124) progressing. Palakkad Proj AE 3
23 Aug 2023 40.39 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (464) & FHTC (124) progressing. Palakkad Proj AE 3
22 Aug 2023 40.39 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (464) & FHTC (124) progressing. Palakkad Proj AE 3
21 Aug 2023 40.28 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (474) & FHTC (124) progressing. Palakkad Proj AE 3