Status Date |
Overall Project Status |
Project Officer |
Contact |
05 Sep 2023 |
40.62 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (487) & FHTC (124) progressing. |
Palakkad Proj AE 3 |
|
04 Sep 2023 |
40.46 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (477) & FHTC (124) progressing. |
Palakkad Proj AE 3 |
|
02 Sep 2023 |
40.46 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (477) & FHTC (124) progressing. |
Palakkad Proj AE 3 |
|
01 Sep 2023 |
40.46 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (477) & FHTC (124) progressing. |
Palakkad Proj AE 3 |
|
26 Aug 2023 |
40.46 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (477) & FHTC (124) progressing. |
Palakkad Proj AE 3 |
|
25 Aug 2023 |
40.46 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (477) & FHTC (124) progressing. |
Palakkad Proj AE 3 |
|
24 Aug 2023 |
40.39 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (464) & FHTC (124) progressing. |
Palakkad Proj AE 3 |
|
23 Aug 2023 |
40.39 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (464) & FHTC (124) progressing. |
Palakkad Proj AE 3 |
|
22 Aug 2023 |
40.39 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (464) & FHTC (124) progressing. |
Palakkad Proj AE 3 |
|
21 Aug 2023 |
40.28 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (474) & FHTC (124) progressing. |
Palakkad Proj AE 3 |
|