Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Sep 2023 42.18 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, HTC (455) & FHTC (160) progressing. Palakkad Proj AE 3
18 Sep 2023 41.76 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, HTC (455) & FHTC (160) progressing. Palakkad Proj AE 3
16 Sep 2023 41.76 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, HTC (455) & FHTC (160) progressing. Palakkad Project Dn EE
15 Sep 2023 41.15 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, HTC (483) & FHTC (132) progressing. Palakkad Proj AE 3
14 Sep 2023 41.15 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, HTC (483) & FHTC (132) progressing. Palakkad Proj AE 3
13 Sep 2023 41.01 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, HTC (491) & FHTC (124) progressing. Palakkad Proj AE 3
12 Sep 2023 40.85 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, HTC (491) & FHTC (124) progressing. Palakkad Proj AE 3
11 Sep 2023 40.73 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. road cutting permission issued & work (Kanjirappuzha-Palakkayam-Injikkunnu PWD road)on going, HTC (491) & FHTC (124) progressing. Palakkad Proj AE 3
08 Sep 2023 40.62 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (487) & FHTC (124) progressing. Palakkad Proj AE 3
07 Sep 2023 40.62 Km/70 km completed . Remaining HDPE, DI & GI pipe laying work progressing. Vakkodan GLSR Site -structure & stair case completed, tank roof slab side plastering completed. Compound wall brick work completed & plastering work on going, road restoration work & interconnection work progressing. demand note issued & awaiting for PWD road cutting permission. HTC (487) & FHTC (124) progressing. Palakkad Proj AE 3