Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Jun 2024 Work in progress 119.636/ 174.70 km laying completed. Remaining pipe laying work progressing.3084/8298 House connections completed & 2939 nos Geo tagged & 0 FHTC's. Palakkad Project Dn AEE3
03 Jun 2024 Work in progress 119.636/ 174.70 km laying completed. Remaining pipe laying work progressing.3084/8298 House connections completed & 2939 nos Geo tagged & 0 FHTC's. Palakkad Project Dn AEE3
01 Jun 2024 Work in progress 119.636/ 174.70 km laying completed. Remaining pipe laying work progressing.3065/8298 House connections completed & 2939 nos Geo tagged & 0 FHTC's. Palakkad Project Dn AEE3
31 May 2024 Work in progress 119.593/ 174.70 km laying completed. Remaining pipe laying work progressing.3064/8298 House connections completed & 2939 nos Geo tagged & 0 FHTC's. Palakkad Project Dn AEE3
30 May 2024 Work in progress 119.573/ 174.70 km laying completed. Remaining pipe laying work progressing.3046/8298 House connections completed & 2939 nos Geo tagged & 0 FHTC's. Palakkad Project Dn EE
27 May 2024 Work in progress 119.556/ 174.70 km laying completed. Remaining pipe laying work progressing.3038/8298 House connections completed & 2939 nos Geo tagged & 0 FHTC's. Palakkad Project Dn EE
25 May 2024 Work in progress 119.548/ 174.70 km laying completed. Remaining pipe laying work progressing.3012/8298 House connections completed & 2927 nos Geo tagged & 0 FHTC's. Palakkad Project Dn AEE3
20 May 2024 Work in progress 119.361/ 174.70 km laying completed. Remaining pipe laying work progressing.3012/8298 House connections completed & 2922 nos Geo tagged & 0 FHTC's. Palakkad Project Dn AEE3
13 May 2024 Work in progress 119.361/ 174.70 km laying completed. Remaining pipe laying work progressing.3012/8298 House connections completed & 2922 nos Geo tagged & 0 FHTC's. Palakkad Project Dn AEE3
06 May 2024 Work in progress 119.22416/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). PHC road pokkupadi, concrete work completed. Railway permission obtained.3003/8298 no's House connections completed & 2909 nos Geo tagged & 0 FHTC's, Ongallur plant road levelling work on going. Palakkad Project Dn AEE3