Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
04 Jun 2024 | Work in progress 119.636/ 174.70 km laying completed. Remaining pipe laying work progressing.3084/8298 House connections completed & 2939 nos Geo tagged & 0 FHTC's. | Palakkad Project Dn AEE3 | |
03 Jun 2024 | Work in progress 119.636/ 174.70 km laying completed. Remaining pipe laying work progressing.3084/8298 House connections completed & 2939 nos Geo tagged & 0 FHTC's. | Palakkad Project Dn AEE3 | |
01 Jun 2024 | Work in progress 119.636/ 174.70 km laying completed. Remaining pipe laying work progressing.3065/8298 House connections completed & 2939 nos Geo tagged & 0 FHTC's. | Palakkad Project Dn AEE3 | |
31 May 2024 | Work in progress 119.593/ 174.70 km laying completed. Remaining pipe laying work progressing.3064/8298 House connections completed & 2939 nos Geo tagged & 0 FHTC's. | Palakkad Project Dn AEE3 | |
30 May 2024 | Work in progress 119.573/ 174.70 km laying completed. Remaining pipe laying work progressing.3046/8298 House connections completed & 2939 nos Geo tagged & 0 FHTC's. | Palakkad Project Dn EE | |
27 May 2024 | Work in progress 119.556/ 174.70 km laying completed. Remaining pipe laying work progressing.3038/8298 House connections completed & 2939 nos Geo tagged & 0 FHTC's. | Palakkad Project Dn EE | |
25 May 2024 | Work in progress 119.548/ 174.70 km laying completed. Remaining pipe laying work progressing.3012/8298 House connections completed & 2927 nos Geo tagged & 0 FHTC's. | Palakkad Project Dn AEE3 | |
20 May 2024 | Work in progress 119.361/ 174.70 km laying completed. Remaining pipe laying work progressing.3012/8298 House connections completed & 2922 nos Geo tagged & 0 FHTC's. | Palakkad Project Dn AEE3 | |
13 May 2024 | Work in progress 119.361/ 174.70 km laying completed. Remaining pipe laying work progressing.3012/8298 House connections completed & 2922 nos Geo tagged & 0 FHTC's. | Palakkad Project Dn AEE3 | |
06 May 2024 | Work in progress 119.22416/ 174.70 km laying completed. Remaining pipe laying work progressing, KRFB ( Pattambi -kulappully road) 90% completed at 8 locations alignment to be fixed by KRFB at 2 location by RBDCK, Vadanamkurussi - Karakkad PWD road work on going(90% completed), Pattambi-cherpulassery laying ongoing (95% completed). PHC road pokkupadi, concrete work completed. Railway permission obtained.3003/8298 no's House connections completed & 2909 nos Geo tagged & 0 FHTC's, Ongallur plant road levelling work on going. | Palakkad Project Dn AEE3 |