Status Date Overall Project Status Project Officer Contact
01 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottameu GLSR have been completed Palakkad Proj AE 3
30 Apr 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottameu GLSR have been completed Palakkad Proj AE 3
29 Apr 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottameu GLSR have been completed Palakkad Proj AE 3
27 Apr 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottameu GLSR have been completed Palakkad Proj AE 3
25 Apr 2024 Intake well - All works completed. Booster pump house- All works are completed, and the compound wall is completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottameu GLSR have been completed Palakkad Proj AE 3
24 Apr 2024 Intake well - All works completed. Booster pump house- All works are completed, and the compound wall is completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottameu GLSR have been completed. Palakkad Proj AE 3
23 Apr 2024 Intake well - All works completed. Booster pump house- All works are completed, and the compound wall is completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottameu GLSR have been completed. Palakkad Proj AE 3
22 Apr 2024 Intake well - All works completed. Booster pump house- All works are completed, and the compound wall is completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipe line CWGM from WTP to Kottameu GLSR has been completed. Palakkad Proj AE 3
20 Apr 2024 Intake well - All works completed. Booster pump house- All works are completed, and the compound wall is completed. RWPM -5819.22m completed. Road to WTP restoration work completed. WTP- All works except the sludge disposal system - scour line pipe laying is ongoing, landscaping is ongoing and supply of filled chlorine tonner was completed. CWGM- 250 mm DI pipe 522.9 m arranged from Division store Palakkad 477.8 m laid, balance pipes to be supplied and laid by the contractor. Palakkad Proj AE 3
19 Apr 2024 Intake well - All works completed. Booster pump house- All works are completed, and the compound wall is completed. RWPM -5819.22m completed. Road to WTP restoration work completed. WTP- All works except the sludge disposal system - scour line pipe laying is ongoing, landscaping is ongoing and supply of filled chlorine tonner was completed. CWGM- 250 mm DI pipe 522.9 m arranged from Division store Palakkad 477.8 m laid, balance pipes to be supplied and laid by the contractor. Palakkad Proj AE 3