| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 02 Sep 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- Supplied 250 mm DI CWGM pipeline and laying in progress from WTP to Kottamedu GLSR. | Palakkad Proj AE 3 | |
| 23 Aug 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 22 Aug 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 20 Aug 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 17 Aug 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 15 Aug 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 13 Aug 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 10 Aug 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 05 Aug 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 29 Jul 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 |