Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed Palakkad Proj AE 3
14 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed Palakkad Proj AE 3
13 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed Palakkad Proj AE 3
10 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed Palakkad Proj AE 3
09 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed Palakkad Proj AE 3
08 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed Palakkad Proj AE 3
07 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed Palakkad Proj AE 3
06 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottameu GLSR have been completed Palakkad Proj AE 3
03 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottameu GLSR have been completed Palakkad Proj AE 3
02 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottameu GLSR have been completed Palakkad Proj AE 3