| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 15 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 14 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 13 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 10 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 09 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 08 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 07 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 06 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottameu GLSR have been completed | Palakkad Proj AE 3 | |
| 03 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottameu GLSR have been completed | Palakkad Proj AE 3 | |
| 02 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottameu GLSR have been completed | Palakkad Proj AE 3 |