| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 22 Jun 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 18 Jun 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 15 Jun 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 10 Jun 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 07 Jun 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 05 Jun 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 04 Jun 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 03 Jun 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 01 Jun 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 31 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 |