Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 Oct 2024 ALL WORKS COMPLETED. Palakkad Proj AE 3
29 Oct 2024 WTP- Supplied 250 mm DI CWGM pipeline and laid from WTP to Kottamedu GLSR.Intake well - All works completed. 5LL Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed.For electric connection KSEB charge deposited. Palakkad Proj AE 3
28 Oct 2024 WTP- Supplied 250 mm DI CWGM pipeline and laid from WTP to Kottamedu GLSR.Intake well - All works completed. 5LL Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed.For electric connection KSEB charge deposited. Palakkad Proj AE 3
25 Oct 2024 WTP- Supplied 250 mm DI CWGM pipeline and laid from WTP to Kottamedu GLSR.Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed.For electric connection KSEB work is going on. Palakkad Proj AE 3
23 Oct 2024 Anchor block work & restoration work in progressing.WTP- Supplied 250 mm DI CWGM pipeline and laid from WTP to Kottamedu GLSR.Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. Palakkad Proj AE 3
22 Oct 2024 Anchor block work & restoration work in progressing.WTP- Supplied 250 mm DI CWGM pipeline and laid from WTP to Kottamedu GLSR.Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. Palakkad Proj AE 3
21 Oct 2024 Anchor block work & restoration work in progressing.WTP- Supplied 250 mm DI CWGM pipeline and laid from WTP to Kottamedu GLSR.Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. Palakkad Proj AE 3
18 Oct 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- Supplied 250 mm DI CWGM pipeline and laying in progress from WTP to Kottamedu GLSR. Anchor work in progressing. Palakkad Proj AE 3
16 Oct 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- Supplied 250 mm DI CWGM pipeline and laying in progress from WTP to Kottamedu GLSR. Anchor work in progressing. Palakkad Proj AE 3
14 Oct 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- Supplied 250 mm DI CWGM pipeline and laying in progress from WTP to Kottamedu GLSR. Anchor work in progressing. Palakkad Proj AE 3