| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 30 Oct 2024 | ALL WORKS COMPLETED. | Palakkad Proj AE 3 | |
| 29 Oct 2024 | WTP- Supplied 250 mm DI CWGM pipeline and laid from WTP to Kottamedu GLSR.Intake well - All works completed. 5LL Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed.For electric connection KSEB charge deposited. | Palakkad Proj AE 3 | |
| 28 Oct 2024 | WTP- Supplied 250 mm DI CWGM pipeline and laid from WTP to Kottamedu GLSR.Intake well - All works completed. 5LL Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed.For electric connection KSEB charge deposited. | Palakkad Proj AE 3 | |
| 25 Oct 2024 | WTP- Supplied 250 mm DI CWGM pipeline and laid from WTP to Kottamedu GLSR.Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed.For electric connection KSEB work is going on. | Palakkad Proj AE 3 | |
| 23 Oct 2024 | Anchor block work & restoration work in progressing.WTP- Supplied 250 mm DI CWGM pipeline and laid from WTP to Kottamedu GLSR.Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. | Palakkad Proj AE 3 | |
| 22 Oct 2024 | Anchor block work & restoration work in progressing.WTP- Supplied 250 mm DI CWGM pipeline and laid from WTP to Kottamedu GLSR.Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. | Palakkad Proj AE 3 | |
| 21 Oct 2024 | Anchor block work & restoration work in progressing.WTP- Supplied 250 mm DI CWGM pipeline and laid from WTP to Kottamedu GLSR.Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. | Palakkad Proj AE 3 | |
| 18 Oct 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- Supplied 250 mm DI CWGM pipeline and laying in progress from WTP to Kottamedu GLSR. Anchor work in progressing. | Palakkad Proj AE 3 | |
| 16 Oct 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- Supplied 250 mm DI CWGM pipeline and laying in progress from WTP to Kottamedu GLSR. Anchor work in progressing. | Palakkad Proj AE 3 | |
| 14 Oct 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- Supplied 250 mm DI CWGM pipeline and laying in progress from WTP to Kottamedu GLSR. Anchor work in progressing. | Palakkad Proj AE 3 |