| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 22 Feb 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5414.85 m completed. Road to WTP restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed. CWGM- 250 mm DI pipe 522.9 m arranged from Division store Palakkad 470 m laid, balance pipes to be supplied and laid by the contractor. | Palakkad Project Dn EE | |
| 21 Feb 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5375.35 m completed. Road to WTP restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed. CWGM- 250 mm DI pipe 522.9 m arranged from Division store Palakkad 470 m laid, balance pipes to be supplied and laid by the contractor. | Palakkad Project Dn EE | |
| 20 Feb 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5347.85 m completed. Road to WTP restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed. CWGM- 250 mm DI pipe 522.9 m arranged from Division store Palakkad 470 m laid, balance pipes to be supplied and laid by the contractor. | Palakkad Project Dn EE | |
| 19 Feb 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5298.35 m completed. Road to WTP restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed. CWGM- 250 mm DI pipe 522.9 m arranged from Division store Palakkad 470 m laid, balance pipes to be supplied and laid by the contractor. | Palakkad Project Dn EE | |
| 17 Feb 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5204.85 m completed. Road to WTP restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed. CWGM- 250 mm DI pipe 522.9 m arranged from Division store Palakkad 470 m laid, balance pipes to be supplied and laid by the contractor. | Palakkad Project Dn EE | |
| 16 Feb 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5133.35 m completed. Road to WTP restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed. CWGM- 250 mm DI pipe 522.9 m arranged from Division store Palakkad 470 m laid, balance pipes to be supplied and laid by the contractor. | Palakkad Project Dn EE | |
| 15 Feb 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5116.85 m completed. Road to WTP restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed. CWGM- 250 mm DI pipe 522.9 m arranged from Division store Palakkad 470 m laid, balance pipes to be supplied and laid by the contractor. | Palakkad Project Dn EE | |
| 14 Feb 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5094.85 m completed. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Project Dn EE | |
| 13 Feb 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5083.85 m completed. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Project Dn EE | |
| 12 Feb 2024 | Intake well - All works completed. Booster Pump house- All works completed, compound wall completed. RWPM -5072.85 m completed. road to wtp restoration work completed, WTP- All works except sludge disposal system, landscaping and supply of filled chlorine tonner completed . CWGM- 250 mm DI pipe 522.9 m arranged from Division store palakkad 470 m laid, balance pipes to be supplied and laid by contractor. | Palakkad Project Dn EE |