| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 30 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 28 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 27 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 25 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 24 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 | |
| 22 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed. | Palakkad Proj AE 3 | |
| 20 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed. | Palakkad Proj AE 3 | |
| 18 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed. | Palakkad Proj AE 3 | |
| 17 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed. | Palakkad Proj AE 3 | |
| 16 May 2024 | Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed | Palakkad Proj AE 3 |