Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed Palakkad Proj AE 3
28 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed Palakkad Proj AE 3
27 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed Palakkad Proj AE 3
25 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed Palakkad Proj AE 3
24 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed Palakkad Proj AE 3
22 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying and laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed. Palakkad Proj AE 3
20 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed. Palakkad Proj AE 3
18 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed. Palakkad Proj AE 3
17 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed. Palakkad Proj AE 3
16 May 2024 Intake well - All works completed. Booster pump house- All works and the compound wall are completed. RWPM -completed. Road to WTP restoration work completed. WTP- All works except supplying laying 250 mm DI pipeline CWGM from WTP to Kottamedu GLSR have been completed Palakkad Proj AE 3